Challenges in Cost Estimation under Uncertainty—A Case Study of the Decommissioning of Barsebäck Nuclear Power Plant

Author

Listed:
  • Olav Torp

    (Department of Civil and Transport Engineering, Norwegian University of Science and Technology, Trondheim 7491, Norway)

  • Ole Jonny Klakegg

    (Department of Civil and Transport Engineering, Norwegian University of Science and Technology, Trondheim 7491, Norway)

Abstract

Cost estimation is an important part of project planning. Over the years different approaches have developed, taking uncertainty into account in the cost estimation processes in order to tackle the dynamic nature of projects. However, when implementing these approaches, some challenges have been revealed. The aim in a cost estimation process is to establish a realistic overview of the total project costs and its uncertainties. Even though tools and methods for taking uncertainty into account are implemented, projects with cost overruns are often seen. In this paper we look into some challenges with the practice in cost estimation processes and identify possible improvements to overcome them. The purpose of this paper is to illustrate better solutions to some of the major weaknesses identified in current cost estimation practice. We use a case study of decommissioning of Barsebäck Nuclear Power Plant to illustrate how to overcome these challenges. First of all, this is an interesting case with challenges related to the project and the cost estimation process, given the complexity in the situation and that very few have experiences related to decommission of nuclear power plants. Second, we applied an approach that is not yet commonly used to develop cost estimates for this kind of projects. The paper concludes that it is possible to improve the results of uncertainty analysis of cost estimates. A well prepared process, with a suitable group of experts that go through a well-structured process, focusing both on risks and opportunities and using a top-down approach can compensate for some of the challenges related to cost estimation under uncertainty.

Suggested Citation

  • Olav Torp & Ole Jonny Klakegg, 2016. "Challenges in Cost Estimation under Uncertainty—A Case Study of the Decommissioning of Barsebäck Nuclear Power Plant," Administrative Sciences, MDPI, vol. 6(4), pages 1-21, October.
  • Handle: RePEc:gam:jadmsc:v:6:y:2016:i:4:p:14-:d:80931
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/2076-3387/6/4/14/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/2076-3387/6/4/14/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Bent Flyvbjerg & Mette K. Skamris holm & Søren L. Buhl, 2003. "How common and how large are cost overruns in transport infrastructure projects?," Transport Reviews, Taylor & Francis Journals, vol. 23(1), pages 71-88, January.
    2. Flyvbjerg,Bent & Bruzelius,Nils & Rothengatter,Werner, 2003. "Megaprojects and Risk," Cambridge Books, Cambridge University Press, number 9780521009461.
    3. Ansar, Atif & Flyvbjerg, Bent & Budzier, Alexander & Lunn, Daniel, 2014. "Should we build more large dams? The actual costs of hydropower megaproject development," Energy Policy, Elsevier, vol. 69(C), pages 43-56.
    4. Brun, Wibecke & Teigen, Karl Halvor, 1988. "Verbal probabilities: Ambiguous, context-dependent, or both?," Organizational Behavior and Human Decision Processes, Elsevier, vol. 41(3), pages 390-404, June.
    5. Williams, Terry, 1995. "A classified bibliography of recent research relating to project risk management," European Journal of Operational Research, Elsevier, vol. 85(1), pages 18-38, August.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Rizki Firmansyah Setya Budi & Moch. Djoko Birmano & Elok Satiti Amitayani, 2021. "Selection of Large-scale Nuclear Power Plant Based on Economic and Reliability Aspects in Indonesian Power System," International Journal of Energy Economics and Policy, Econjournals, vol. 11(5), pages 42-51.
    2. Invernizzi, Diletta Colette & Locatelli, Giorgio & Brookes, Naomi & Davis, Allison, 2020. "Qualitative comparative analysis as a method for project studies: The case of energy infrastructure," Renewable and Sustainable Energy Reviews, Elsevier, vol. 133(C).

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Cantarelli, C.C. & Flyvbjerg, B. & Buhl, S.L., 2012. "Geographical variation in project cost performance: the Netherlands versus worldwide," Journal of Transport Geography, Elsevier, vol. 24(C), pages 324-331.
    2. Holz-Rau, Christian & Scheiner, Joachim, 2011. "Safety and travel time in cost-benefit analysis: A sensitivity analysis for North Rhine-Westphalia," Transport Policy, Elsevier, vol. 18(2), pages 336-346, March.
    3. Love, Peter E.D. & Ika, Lavagnon A. & Ahiaga-Dagbui, Dominic D., 2019. "On de-bunking ‘fake news’ in a post truth era: Why does the Planning Fallacy explanation for cost overruns fall short?," Transportation Research Part A: Policy and Practice, Elsevier, vol. 126(C), pages 397-408.
    4. Al-Noor Abdullah & Sanzidur Rahman, 2021. "Social Impacts of a Mega-Dam Project as Perceived by Local, Resettled and Displaced Communities: A Case Study of Merowe Dam, Sudan," Economies, MDPI, vol. 9(4), pages 1-32, September.
    5. Atif Ansar & Bent Flyvbjerg & Alexander Budzier & Daniel Lunn, 2016. "Does infrastructure investment lead to economic growth or economic fragility? Evidence from China," Oxford Review of Economic Policy, Oxford University Press and Oxford Review of Economic Policy Limited, vol. 32(3), pages 360-390.
    6. Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012. "Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases," Transport Policy, Elsevier, vol. 22(C), pages 49-56.
    7. Brookes, Naomi J. & Locatelli, Giorgio, 2015. "Power plants as megaprojects: Using empirics to shape policy, planning, and construction management," Utilities Policy, Elsevier, vol. 36(C), pages 57-66.
    8. Agnieszka Huterska, 2017. "Public-Private Partnership in Building Sustainable Development of the Kuyavian-Pomeranian Voivodship," European Journal of Interdisciplinary Studies Articles, Revistia Research and Publishing, vol. 3, September.
    9. Petter Osmundsen & Kristin Helen Roll, 2016. "Rig Rates and Drilling Speed: Reinforcing Effects," CESifo Working Paper Series 5895, CESifo.
    10. Abeysekara, Baudhi & Perera, Piyaruwan & Chhipi Shrestha, Gyan Kumar & Gunaruwan, Lalithasiri & Kumarage, Amal & Sadiq, Rehan & Hewage, Kasun, 2021. "Improving the capital deployment efficiency: An infrastructure investment planning process in transportation project," Research in Transportation Economics, Elsevier, vol. 88(C).
    11. Natalya Sergeeva & Johan Ninan, 2023. "Comparisons as a discursive tool: shaping megaproject narratives in the United Kingdom," Policy and Society, Darryl S. Jarvis and M. Ramesh, vol. 42(2), pages 197-211.
    12. Santanu Chatterjee & Olaf Posch & Dennis Wesselbaum, 2017. "Delays in Public Goods," Working Papers 1702, University of Otago, Department of Economics, revised Feb 2017.
    13. Steen Lichtenberg, 2016. "Successful Control of Major Project Budgets," Administrative Sciences, MDPI, vol. 6(3), pages 1-14, July.
    14. Christos Ellinas & Christos Nicolaides & Naoki Masuda, 2022. "Mitigation strategies against cascading failures within a project activity network," Journal of Computational Social Science, Springer, vol. 5(1), pages 383-400, May.
    15. Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
    16. Jorge Valido, 2020. "Large Infrastructure Investments: Financing Mechanisms and Incentives in Decentralised Countries," Fiscal Studies, John Wiley & Sons, vol. 41(4), pages 905-921, December.
    17. Atif Ansar & Martin Pohlers, 2014. "Fluid populations, immobile assets: Synchronizing infrastructure investments with shifting demography," International Area Studies Review, Center for International Area Studies, Hankuk University of Foreign Studies, vol. 17(2), pages 222-248, June.
    18. Giorgio Locatelli, 2018. "Why are Megaprojects, Including Nuclear Power Plants, Delivered Overbudget and Late? Reasons and Remedies," Papers 1802.07312, arXiv.org.
    19. Øglend, Atle & Osmundsen, Petter & Lorentzen, Sindre, 2016. "Cost Overrun at the Norwegian Continental Shelf: The element of surprise," UiS Working Papers in Economics and Finance 2016/3, University of Stavanger.
    20. Ackermann, Fran & Howick, Susan & Quigley, John & Walls, Lesley & Houghton, Tom, 2014. "Systemic risk elicitation: Using causal maps to engage stakeholders and build a comprehensive view of risks," European Journal of Operational Research, Elsevier, vol. 238(1), pages 290-299.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jadmsc:v:6:y:2016:i:4:p:14-:d:80931. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.