Hybrid flow shop scheduling considering machine electricity consumption cost

Author

Listed:
  • Luo, Hao
  • Du, Bing
  • Huang, George Q.
  • Chen, Huaping
  • Li, Xiaolin

Abstract

Hybrid flow shop (HFS) scheduling has been extensively examined and the main objective has been to improve production efficiency. However, limited attention has been paid to the consideration of energy consumption with the advent of green manufacturing. This paper proposes a new ant colony optimization (MOACO) meta-heuristic considering not only production efficiency but also electric power cost (EPC) with the presence of time-of-use (TOU) electricity prices. The solution is encoded as a permutation of jobs. A list schedule algorithm is applied to construct the sequence by artificial ants and generate a complete schedule. A right-shift procedure is then used to adjust the start time of operations aiming to minimize the EPC for the schedule. In terms of theoretical research aspect, the results from computational experiments indicate that the efficiency and effectiveness of the proposed MOACO are comparable to NSGA-II and SPEA2. In terms of practical application aspect, the guideline about how to set preference over multiple objectives has been studied. This result has significant managerial implications in real life production. The parameter analysis also shows that durations of TOU periods and processing speed of machines have great influence on scheduling results as longer off-peak period and use of faster machines provide more flexibility for shifting high-energy operations to off-peak periods.

Suggested Citation

  • Luo, Hao & Du, Bing & Huang, George Q. & Chen, Huaping & Li, Xiaolin, 2013. "Hybrid flow shop scheduling considering machine electricity consumption cost," International Journal of Production Economics, Elsevier, vol. 146(2), pages 423-439.
  • Handle: RePEc:eee:proeco:v:146:y:2013:i:2:p:423-439
    DOI: 10.1016/j.ijpe.2013.01.028
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0925527313000467
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ijpe.2013.01.028?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Dessouky, Maged M. & Dessouky, Mohamed I. & Verma, Sushil K., 1998. "Flowshop scheduling with identical jobs and uniform parallel machines," European Journal of Operational Research, Elsevier, vol. 109(3), pages 620-631, September.
    2. Damodaran, Purushothaman & Kumar Manjeshwar, Praveen & Srihari, Krishnaswami, 2006. "Minimizing makespan on a batch-processing machine with non-identical job sizes using genetic algorithms," International Journal of Production Economics, Elsevier, vol. 103(2), pages 882-891, October.
    3. Ruiz, Rubén & Vázquez-Rodríguez, José Antonio, 2010. "The hybrid flow shop scheduling problem," European Journal of Operational Research, Elsevier, vol. 205(1), pages 1-18, August.
    4. Kurz, Mary E. & Askin, Ronald G., 2003. "Comparing scheduling rules for flexible flow lines," International Journal of Production Economics, Elsevier, vol. 85(3), pages 371-388, September.
    5. Quadt, Daniel & Kuhn, Heinrich, 2007. "A taxonomy of flexible flow line scheduling procedures," European Journal of Operational Research, Elsevier, vol. 178(3), pages 686-698, May.
    6. Kyparisis, George J. & Koulamas, Christos, 2006. "A note on makespan minimization in two-stage flexible flow shops with uniform machines," European Journal of Operational Research, Elsevier, vol. 175(2), pages 1321-1327, December.
    7. T'kindt, Vincent & Monmarche, Nicolas & Tercinet, Fabrice & Laugt, Daniel, 2002. "An Ant Colony Optimization algorithm to solve a 2-machine bicriteria flowshop scheduling problem," European Journal of Operational Research, Elsevier, vol. 142(2), pages 250-257, October.
    8. Logendran, Rasaratnam & deSzoeke, Paula & Barnard, Faith, 2006. "Sequence-dependent group scheduling problems in flexible flow shops," International Journal of Production Economics, Elsevier, vol. 102(1), pages 66-86, July.
    9. Rajendran, Chandrasekharan & Ziegler, Hans, 2004. "Ant-colony algorithms for permutation flowshop scheduling to minimize makespan/total flowtime of jobs," European Journal of Operational Research, Elsevier, vol. 155(2), pages 426-438, June.
    10. Karl Doerner & Walter Gutjahr & Richard Hartl & Christine Strauss & Christian Stummer, 2004. "Pareto Ant Colony Optimization: A Metaheuristic Approach to Multiobjective Portfolio Selection," Annals of Operations Research, Springer, vol. 131(1), pages 79-99, October.
    11. E. Bonabeau & M. Dorigo & G. Theraulaz, 2000. "Inspiration for optimization from social insect behaviour," Nature, Nature, vol. 406(6791), pages 39-42, July.
    12. Logendran, Rasaratnam & Carson, Sara & Hanson, Erik, 2005. "Group scheduling in flexible flow shops," International Journal of Production Economics, Elsevier, vol. 96(2), pages 143-155, May.
    13. J.N.D. Gupta & A.M.A. Hariri & C.N. Potts, 1997. "Scheduling a two-stage hybrid flow shop with parallel machines at the first stage," Annals of Operations Research, Springer, vol. 69(0), pages 171-191, January.
    14. Robert J. Wittrock, 1988. "An Adaptable Scheduling Algorithm for Flexible Flow Lines," Operations Research, INFORMS, vol. 36(3), pages 445-453, June.
    15. Brah, Shaukat A. & Hunsucker, John L., 1991. "Branch and bound algorithm for the flow shop with multiple processors," European Journal of Operational Research, Elsevier, vol. 51(1), pages 88-99, March.
    16. Kurz, Mary E. & Askin, Ronald G., 2004. "Scheduling flexible flow lines with sequence-dependent setup times," European Journal of Operational Research, Elsevier, vol. 159(1), pages 66-82, November.
    17. Loukil, Taicir & Teghem, Jacques & Fortemps, Philippe, 2007. "A multi-objective production scheduling case study solved by simulated annealing," European Journal of Operational Research, Elsevier, vol. 179(3), pages 709-722, June.
    18. Garcia-Martinez, C. & Cordon, O. & Herrera, F., 2007. "A taxonomy and an empirical analysis of multiple objective ant colony optimization algorithms for the bi-criteria TSP," European Journal of Operational Research, Elsevier, vol. 180(1), pages 116-148, July.
    19. Oguz, Ceyda & Zinder, Yakov & Ha Do, Van & Janiak, Adam & Lichtenstein, Maciej, 2004. "Hybrid flow-shop scheduling problems with multiprocessor task systems," European Journal of Operational Research, Elsevier, vol. 152(1), pages 115-131, January.
    20. Loukil, T. & Teghem, J. & Tuyttens, D., 2005. "Solving multi-objective production scheduling problems using metaheuristics," European Journal of Operational Research, Elsevier, vol. 161(1), pages 42-61, February.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Ruiz, Rubén & Vázquez-Rodríguez, José Antonio, 2010. "The hybrid flow shop scheduling problem," European Journal of Operational Research, Elsevier, vol. 205(1), pages 1-18, August.
    2. Amin-Naseri, Mohammad Reza & Beheshti-Nia, Mohammad Ali, 2009. "Hybrid flow shop scheduling with parallel batching," International Journal of Production Economics, Elsevier, vol. 117(1), pages 185-196, January.
    3. Quadt, Daniel & Kuhn, Heinrich, 2007. "Batch scheduling of jobs with identical process times on flexible flow lines," International Journal of Production Economics, Elsevier, vol. 105(2), pages 385-401, February.
    4. Fan Yang & Roel Leus, 2021. "Scheduling hybrid flow shops with time windows," Journal of Heuristics, Springer, vol. 27(1), pages 133-158, April.
    5. Mingxing Li & Ray Y. Zhong & Ting Qu & George Q. Huang, 2022. "Spatial–temporal out-of-order execution for advanced planning and scheduling in cyber-physical factories," Journal of Intelligent Manufacturing, Springer, vol. 33(5), pages 1355-1372, June.
    6. Quadt, Daniel & Kuhn, Heinrich, 2007. "A taxonomy of flexible flow line scheduling procedures," European Journal of Operational Research, Elsevier, vol. 178(3), pages 686-698, May.
    7. Allahverdi, Ali & Ng, C.T. & Cheng, T.C.E. & Kovalyov, Mikhail Y., 2008. "A survey of scheduling problems with setup times or costs," European Journal of Operational Research, Elsevier, vol. 187(3), pages 985-1032, June.
    8. Ruiz, Ruben & Maroto, Concepcion, 2006. "A genetic algorithm for hybrid flowshops with sequence dependent setup times and machine eligibility," European Journal of Operational Research, Elsevier, vol. 169(3), pages 781-800, March.
    9. Bozorgirad, Mir Abbas & Logendran, Rasaratnam, 2013. "Bi-criteria group scheduling in hybrid flowshops," International Journal of Production Economics, Elsevier, vol. 145(2), pages 599-612.
    10. Carlos Paternina-Arboleda & Jairo Montoya-Torres & Milton Acero-Dominguez & Maria Herrera-Hernandez, 2008. "Scheduling jobs on a k-stage flexible flow-shop," Annals of Operations Research, Springer, vol. 164(1), pages 29-40, November.
    11. Pan, Quan-Ke & Gao, Liang & Li, Xin-Yu & Gao, Kai-Zhou, 2017. "Effective metaheuristics for scheduling a hybrid flowshop with sequence-dependent setup times," Applied Mathematics and Computation, Elsevier, vol. 303(C), pages 89-112.
    12. Pan, Quan-Ke & Wang, Ling & Li, Jun-Qing & Duan, Jun-Hua, 2014. "A novel discrete artificial bee colony algorithm for the hybrid flowshop scheduling problem with makespan minimisation," Omega, Elsevier, vol. 45(C), pages 42-56.
    13. Jin, Zhihong & Yang, Zan & Ito, Takahiro, 2006. "Metaheuristic algorithms for the multistage hybrid flowshop scheduling problem," International Journal of Production Economics, Elsevier, vol. 100(2), pages 322-334, April.
    14. Chou, Fuh-Der, 2013. "Particle swarm optimization with cocktail decoding method for hybrid flow shop scheduling problems with multiprocessor tasks," International Journal of Production Economics, Elsevier, vol. 141(1), pages 137-145.
    15. Urlings, Thijs & Ruiz, Rubén & Stützle, Thomas, 2010. "Shifting representation search for hybrid flexible flowline problems," European Journal of Operational Research, Elsevier, vol. 207(2), pages 1086-1095, December.
    16. Kurz, Mary E. & Askin, Ronald G., 2004. "Scheduling flexible flow lines with sequence-dependent setup times," European Journal of Operational Research, Elsevier, vol. 159(1), pages 66-82, November.
    17. Lin, Hung-Tso & Liao, Ching-Jong, 2003. "A case study in a two-stage hybrid flow shop with setup time and dedicated machines," International Journal of Production Economics, Elsevier, vol. 86(2), pages 133-143, November.
    18. Sündüz Dağ, 2013. "An Application On Flowshop Scheduling," Alphanumeric Journal, Bahadir Fatih Yildirim, vol. 1(1), pages 47-56, December.
    19. Weng, Wei & Fujimura, Shigeru, 2012. "Control methods for dynamic time-based manufacturing under customized product lead times," European Journal of Operational Research, Elsevier, vol. 218(1), pages 86-96.
    20. Wen, Charlie & Eksioglu, Sandra Duni & Greenwood, Allen & Zhang, Shu, 2010. "Crane scheduling in a shipbuilding environment," International Journal of Production Economics, Elsevier, vol. 124(1), pages 40-50, March.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:proeco:v:146:y:2013:i:2:p:423-439. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/ijpe .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.