The first asphalt concrete long-life (AC Long Life) project was constructed in Los Angeles County on Route 710 (LA-710) near Long Beach in 2001/2004 and is now over 20 years old. Four more AC Long Life projects have been completed in California since then, three between 2011 and 2014 (TEH-5, SIS-5, SOL-5), and one in 2021/2022 (SAC-5). The goal of these AC Long Life projects was to achieve design lives of 30 years or 40 years (the standard Caltrans asphalt pavement design life was 20 years at the time). Measures taken to achieve those lives included the use of performance-related specifications for job mix formula approvals, higher compaction requirements, and the use of a three-layer asphalt concrete system for structural capacity. These measures required additional costs. Calculations indicate that the longer lives will result in life cycle cost reductions if they achieve the design lives. Hence, periodic performance evaluations are important, which is the purpose of this technical memorandum. Extensive material sampling and structural evaluation were conducted regularly on the LA-710 and TEH-5projects. This technical memorandum reviews the available performance data, summarizes the material testing and structural evaluation data for the LA-710 and TEH-5 projects, and compares the as-built materials with statewide medians. The cracking, patching, roughness (IRI), and rutting data revealed that these projects had all performed very well in general at respective 10- to 20-year milestones. No rehabilitation and only one minor maintenance activity has been performed on LA-710, and no maintenance/rehabilitation activity has been performed on the 10-year-old projects. Analysis of the LA-710 and TEH-5 deflection data suggests some densification (not to the extent of crushing) and aging in the asphalt-bound layers but no signs of traffic-induced damage. Laboratory test data on between-wheelpath specimens from the TEH-5 project indicate that the as-built materials in general have better fatigue performance, lower stiffness, and lower permanent deformation performance than the statewide median materials tested during mix design. Given the fact that only minor rutting has been observed in these projects, the as-built materials are believed to be good examples of mixes with balanced performance, with a few exceptions.
Suggested Citation
Wu, Rongzong & Lea, Jeremy & Harvey, John & Guada, Irwin & Rahman, Mohammad, 2026.
"Twenty-Year Performance Review of Asphalt Concrete Long-LifePavements with Performance-Related Specifications,"
Institute of Transportation Studies, Working Paper Series
qt8b52q3s4, Institute of Transportation Studies, UC Davis.
Handle:
RePEc:cdl:itsdav:qt8b52q3s4
Download full text from publisher
Corrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:cdl:itsdav:qt8b52q3s4. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
We have no bibliographic references for this item. You can help adding them by using this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Lisa Schiff (email available below). General contact details of provider: https://edirc.repec.org/data/itucdus.html .
Please note that corrections may take a couple of weeks to filter through
the various RePEc services.