Prioritizing collaborative scheduling practices based on their impact on project performance

Author

Listed:
  • Chuanni He
  • Min Liu
  • Thais da C. L. Alves
  • Natalie M. Scala
  • Simon M. Hsiang

Abstract

Collaborative scheduling (CS) and related practices impact the performance of construction projects which can be measured by key performance indicators (KPIs). However, little is known about which of these practices are implemented and how their combined implementation might impact KPIs. The objectives of this research are to identify perceptions of CS practices that drive project performance, define CS practices used by industry that impact KPIs, and establish practices that are more commonly implemented and have a higher potential to positively impact KPIs. The research team conducted a nationwide survey in the United States and obtained 241 usable responses. Utilizing an information theory approach to measure the uncertainty of implementation and impact of each practice, the research built a set of Chow–Liu tree models to determine the most efficient sequence of actions to improve CS. Results indicate that meeting owners’ expectation throughout the life-cycle of the project from design through construction and commissioning, using the schedule to support a strong project culture, and an effective communication plan were the top CS levers for overall KPI improvement. An innovative method was developed to help construction project managers discover the value of each CS practice, the relation between CS practices, and CS practices’ influence to project KPIs so that managers can improve KPIs efficiently by prioritizing their CS practices according to their own project needs.

Suggested Citation

  • Chuanni He & Min Liu & Thais da C. L. Alves & Natalie M. Scala & Simon M. Hsiang, 2022. "Prioritizing collaborative scheduling practices based on their impact on project performance," Construction Management and Economics, Taylor & Francis Journals, vol. 40(7-8), pages 618-637, August.
  • Handle: RePEc:taf:conmgt:v:40:y:2022:i:7-8:p:618-637
    DOI: 10.1080/01446193.2022.2048042
    as

    Download full text from publisher

    File URL: http://hdl.handle.net/10.1080/01446193.2022.2048042
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1080/01446193.2022.2048042?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:taf:conmgt:v:40:y:2022:i:7-8:p:618-637. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Chris Longhurst (email available below). General contact details of provider: http://www.tandfonline.com/RCME20 .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.