The problem faced by one of the private construction companies in Jakarta, Indonesia is the delay in completing the grounding and lightning protection installation project. This delay resulted in both material and immaterial losses for the company. Factors that are thought to cause delays in this grounding and lightning protection installation project include man, machine, material, and environment factors. The method used in this research is the Critical Path Method (CPM) and Crashing method to accelerate the project duration and determine the effective time and cost that can be used to complete the grounding and lightning protection installation project and the root cause analysis method with fishbone diagrams and 5 why analysis as tools to find out the root causes of problems and formulate corrective actions that may be taken by the company. The most effective and efficient acceleration alternative in terms of time and cost that can be applied by the company is the alternative of additional labour. The additional labour alternative is able to reduce the duration of work with the smallest additional cost compared to other alternatives. Meanwhile, the factors that cause delays in project work can be seen from the root causes of each factor. The root cause of each factor is then used as the basis for formulating corrective actions that can be taken by the company.
Suggested Citation
Neng Anita Setiawati & Rosalendro Eddy Nugroho, 2023.
"Evaluation of Time, Cost, and Factors Causing Delay of Grounding and Lightning Protection Installation Project,"
European Journal of Business and Management Research, European Open Science, vol. 8(4), pages 74-81, July.
Handle:
RePEc:epw:ejbmr0:v:8:y:2023:i:4:id:52005
DOI: 10.24018/ejbmr.2023.8.4.2005
Download full text from publisher
Corrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:epw:ejbmr0:v:8:y:2023:i:4:id:52005. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
We have no bibliographic references for this item. You can help adding them by using this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Support Team (email available below). General contact details of provider: https://eu-opensci.org/index.php/ejbmr .
Please note that corrections may take a couple of weeks to filter through
the various RePEc services.