A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates

Author

Listed:
  • Ihsan Issa Ahmad Hosani

    (University of Sharjah)

  • Fikri T. Dweiri

    (University of Sharjah)

  • Udechukwu Ojiako

    (University of Sharjah)

Abstract

Cost performance is a concern particularly for Complex multi-stakeholder projects in the form of critical infrastructure. Evidence suggests that critical infrastructure projects in the United Arab Emirates (‘UAE’) experience substantial cost overruns. Cost overruns and its consequences in terms of project failure can lead to substantial negative and unintended consequences on infrastructure project systems, especially noting that it is sector characterized by substantial interrelatedness and interdependence between different projects. For these reasons, understanding the causes and possible solutions to cost overruns as a form of project failure is of paramount importance. To undertake such a study, data were collected through structured questionnaire survey (focused on 44 common factors), of various project stakeholders with analysis focusing on frequency, severity and importance indices. Findings suggest five major reasons leading to cost overruns in UAE infrastructure projects as ‘Delays in decisions making by approval authorities’, ‘Changes in client requirements’, ‘Construction cost underestimation’, ‘Poor site management’ and ‘Frequency of variation orders and additional works’.

Suggested Citation

  • Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 0. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 0, pages 1-10.
  • Handle: RePEc:spr:ijsaem:v::y::i::d:10.1007_s13198-020-00979-8
    DOI: 10.1007/s13198-020-00979-8
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1007/s13198-020-00979-8
    File Function: Abstract
    Download Restriction: Access to the full text of the articles in this series is restricted.

    File URL: https://libkey.io/10.1007/s13198-020-00979-8?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Skamris, Mette K. & Flyvbjerg, Bent, 1997. "Inaccuracy of traffic forecasts and cost estimates on large transport projects," Transport Policy, Elsevier, vol. 4(3), pages 141-146, July.
    2. Bent Flyvbjerg, 2013. "Quality Control and Due Diligence in Project Management: Getting Decisions Right by Taking the Outside View," Papers 1302.2544, arXiv.org.
    3. P. A. Koushki & K. Al-Rashid & N. Kartam, 2005. "Delays and cost increases in the construction of private residential projects in Kuwait," Construction Management and Economics, Taylor & Francis Journals, vol. 23(3), pages 285-294.
    4. Hugo Priemus & Bent Flyvbjerg & Bert van Wee (ed.), 2008. "Decision-Making on Mega-Projects," Books, Edward Elgar Publishing, number 4112.
    5. Bent Flyvbjerg, 2007. "Policy and Planning for Large-Infrastructure Projects: Problems, Causes, Cures," Environment and Planning B, , vol. 34(4), pages 578-597, August.
    6. Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012. "Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases," Transport Policy, Elsevier, vol. 22(C), pages 49-56.
    7. Arshi Shakeel Faridi & Sameh Monir El-Sayegh, 2006. "Significant factors causing delay in the UAE construction industry," Construction Management and Economics, Taylor & Francis Journals, vol. 24(11), pages 1167-1176.
    8. Ram Singh, 2009. "Delays and Cost Overruns in Infrastructure Projects -- An Enquiry into Extents, Causes and Remedies," Working papers 181, Centre for Development Economics, Delhi School of Economics.
    9. Dejan Makovšek & Polona Tominc & Klavdij Logožar, 2012. "A cost performance analysis of transport infrastructure construction in Slovenia," Transportation, Springer, vol. 39(1), pages 197-214, January.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 2020. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 11(6), pages 1250-1259, December.
    2. Verweij, Stefan & van Meerkerk, Ingmar & Korthagen, Iris A., 2015. "Reasons for contract changes in implementing Dutch transportation infrastructure projects: An empirical exploration," Transport Policy, Elsevier, vol. 37(C), pages 195-202.
    3. Love, Peter E.D. & Ahiaga-Dagbui, Dominic D., 2018. "Debunking fake news in a post-truth era: The plausible untruths of cost underestimation in transport infrastructure projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 113(C), pages 357-368.
    4. Molinari, Laura & Haezendonck, Elvira & Mabillard, Vincent, 2023. "Cost overruns of Belgian transport infrastructure projects: Analyzing variations over three land transport modes and two project phases," Transport Policy, Elsevier, vol. 134(C), pages 167-179.
    5. Miranda Sarmento, J.J., 2014. "Public private partnerships," Other publications TiSEM c7d4c978-234c-4f88-83ed-1, Tilburg University, School of Economics and Management.
    6. Odeck, James, 2014. "Do reforms reduce the magnitudes of cost overruns in road projects? Statistical evidence from Norway," Transportation Research Part A: Policy and Practice, Elsevier, vol. 65(C), pages 68-79.
    7. Edyta Plebankiewicz, 2018. "Model of Predicting Cost Overrun in Construction Projects," Sustainability, MDPI, vol. 10(12), pages 1-14, November.
    8. Chiara Pancotti & Matteo Pedralli & Geert Smit & Silvia Vignetti, 2020. "Understanding transport project appraisal in its institutional dimension," Working Papers 201902, CSIL Centre for Industrial Studies.
    9. Cathy Macharis & Peter Nijkamp, 2013. "Multi-actor and multi-criteria analysis in evaluating mega-projects," Chapters, in: Hugo Priemus & Bert van Wee (ed.), International Handbook on Mega-Projects, chapter 11, pages 242-266, Edward Elgar Publishing.
    10. Yazan Issa Abu Aisheh, 2021. "Lessons Learned, Barriers, and Improvement Factors for Mega Building Construction Projects in Developing Countries: Review Study," Sustainability, MDPI, vol. 13(19), pages 1-17, September.
    11. Martijn Leijten, 2013. "Real-world decision-making on mega-projects: politics, bias and strategic behaviour," Chapters, in: Hugo Priemus & Bert van Wee (ed.), International Handbook on Mega-Projects, chapter 4, pages 57-82, Edward Elgar Publishing.
    12. Thomopoulos, N. & Grant-Muller, S. & Tight, M.R., 2009. "Incorporating equity considerations in transport infrastructure evaluation: Current practice and a proposed methodology," Evaluation and Program Planning, Elsevier, vol. 32(4), pages 351-359, November.
    13. Chong, Uven & Hopkins, Omar, 2016. "An international experience on the evolution of road costs during the project life cycle," Transport Policy, Elsevier, vol. 48(C), pages 60-66.
    14. Awojobi, Omotola & Jenkins, Glenn P., 2016. "Managing the cost overrun risks of hydroelectric dams: An application of reference class forecasting techniques," Renewable and Sustainable Energy Reviews, Elsevier, vol. 63(C), pages 19-32.
    15. Jarosław Górecki & Manuel Díaz-Madroñero, 2020. "Who Risks and Wins?—Simulated Cost Variance in Sustainable Construction Projects," Sustainability, MDPI, vol. 12(8), pages 1-31, April.
    16. Lundberg, Mattias & Jenpanitsub, Anchalee & Pyddoke, Roger, 2011. "Cost overruns in Swedish transport projects," Working papers in Transport Economics 2011:11, CTS - Centre for Transport Studies Stockholm (KTH and VTI).
    17. Willem K Korthals Altes, 2010. "The Financial Estimates and Results of Servicing Land in the Netherlands," Environment and Planning B, , vol. 37(5), pages 929-941, October.
    18. Chi, Sae & Bunker, Jonathan, 2021. "An Australian perspective on real-life cost-benefit analysis and assessment frameworks for transport infrastructure investments," Research in Transportation Economics, Elsevier, vol. 88(C).
    19. Zhou, You & Zhang, Lingzhu & Chiaradia, Alain J F, 2021. "An adaptation of reference class forecasting for the assessment of large-scale urban planning vision, a SEM-ANN approach to the case of Hong Kong Lantau tomorrow," Land Use Policy, Elsevier, vol. 109(C).
    20. Miller, Michael & Szimba, Eckhard, 2015. "How to avoid unrealistic appraisal results? A concept to reflect the occurrence of risk in the appraisal of transport infrastructure projects," Research in Transportation Economics, Elsevier, vol. 49(C), pages 65-75.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:ijsaem:v::y::i::d:10.1007_s13198-020-00979-8. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.