Managing the Cost Overrun Risks of Hydroelectric Dams: An Application of Reference Class Forecasting Techniques

Author

Listed:
  • Omotola Awojobi

    (Eastern Mediterranean University, North Cyprus)

  • Glenn P. Jenkins

    (Queen’s University, Canada and Eastern Mediterranean University, North Cyprus)

Abstract

Hydropower investments have been subject to intense criticism over environmental issues and the common experience with cost uncertainty. In this study we address the issue of uncertainty in cost projections by applying reference class forecasting (RCF) in order to improve the reliability of costs used for making decisions under uncertainty. This technique makes it possible to closely link contingency estimates to the likely incidence of uncertainty of construction costs for hydroelectric dams. A case study, the Bujagali dam in Uganda, is used to demonstrate how investment appraisal can be enhanced to better account for the risk of cost overruns. While this project has suffered from cost overruns, the net benefits of the dam are still expected to be substantial. We conclude that if historical information from the major financiers of dams is accessible, learning from the past can help to reduce the cost of uncertainty in power planning worldwide.

Suggested Citation

  • Omotola Awojobi & Glenn P. Jenkins, 2015. "Managing the Cost Overrun Risks of Hydroelectric Dams: An Application of Reference Class Forecasting Techniques," Development Discussion Papers 2015-06, JDI Executive Programs.
  • Handle: RePEc:qed:dpaper:278
    as

    Download full text from publisher

    File URL: https://cri-world.com/publications/qed_dp_278.pdf
    Download Restriction: no
    ---><---

    Other versions of this item:

    References listed on IDEAS

    as
    1. Awojobi, Omotola & Jenkins, Glenn P., 2015. "Were the hydro dams financed by the World Bank from 1976 to 2005 worthwhile?," Energy Policy, Elsevier, vol. 86(C), pages 222-232.
    2. Bent Flyvbjerg, 2007. "Policy and Planning for Large-Infrastructure Projects: Problems, Causes, Cures," Environment and Planning B, , vol. 34(4), pages 578-597, August.
    3. Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012. "Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases," Transport Policy, Elsevier, vol. 22(C), pages 49-56.
    4. Daniel Kahneman & Amos Tversky, 2013. "Prospect Theory: An Analysis of Decision Under Risk," World Scientific Book Chapters, in: Leonard C MacLean & William T Ziemba (ed.), HANDBOOK OF THE FUNDAMENTALS OF FINANCIAL DECISION MAKING Part I, chapter 6, pages 99-127, World Scientific Publishing Co. Pte. Ltd..
    5. Ansar, Atif & Flyvbjerg, Bent & Budzier, Alexander & Lunn, Daniel, 2014. "Should we build more large dams? The actual costs of hydropower megaproject development," Energy Policy, Elsevier, vol. 69(C), pages 43-56.
    6. Recchia, Anthony, 2010. "R-Squared Measures for Two-Level Hierarchical Linear Models Using SAS," Journal of Statistical Software, Foundation for Open Access Statistics, vol. 32(c02).
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Ayobami Solomon Oyewo & Javier Farfan & Pasi Peltoniemi & Christian Breyer, 2018. "Repercussion of Large Scale Hydro Dam Deployment: The Case of Congo Grand Inga Hydro Project," Energies, MDPI, vol. 11(4), pages 1-30, April.
    2. Flyvbjerg, Bent & Bester, Dirk W., 2021. "The Cost-Benefit Fallacy: Why Cost-Benefit Analysis Is Broken and How to Fix It," Journal of Benefit-Cost Analysis, Cambridge University Press, vol. 12(3), pages 395-419, October.
    3. Suh, Daniel Y. & Ryerson, Megan S., 2019. "Forecast to grow: Aviation demand forecasting in an era of demand uncertainty and optimism bias," Transportation Research Part E: Logistics and Transportation Review, Elsevier, vol. 128(C), pages 400-416.
    4. Anuja Shaktawat & Shelly Vadhera, 2021. "Risk management of hydropower projects for sustainable development: a review," Environment, Development and Sustainability: A Multidisciplinary Approach to the Theory and Practice of Sustainable Development, Springer, vol. 23(1), pages 45-76, January.
    5. Flyvbjerg, Bent & Ansar, Atif & Budzier, Alexander & Buhl, Søren & Cantarelli, Chantal & Garbuio, Massimo & Glenting, Carsten & Holm, Mette Skamris & Lovallo, Dan & Lunn, Daniel & Molin, Eric & Rønnes, 2018. "Five things you should know about cost overrun," Transportation Research Part A: Policy and Practice, Elsevier, vol. 118(C), pages 174-190.
    6. Callegari, C. & Szklo, A. & Schaeffer, R., 2018. "Cost overruns and delays in energy megaprojects: How big is big enough?," Energy Policy, Elsevier, vol. 114(C), pages 211-220.
    7. Jenkins, G. & Olasehinde-Williams, G. & Baurzhan, S., 2022. "Is there a net economic loss from employing reference class forecasting in the appraisal of hydropower projects?," Renewable and Sustainable Energy Reviews, Elsevier, vol. 159(C).
    8. Lordan-Perret, Rebecca & Bärenbold, Rebekka & Weigt, Hannes & Rosner, Robert, 2023. "An ex-ante method to verify commercial U.S. nuclear power plant decommissioning cost estimates," Energy Economics, Elsevier, vol. 127(PB).
    9. Yakun Zhang & Wenzhe Tang & Colin F. Duffield & Lihai Zhang & Felix Kin Peng Hui, 2021. "Environment Management of Hydropower Development: A Case Study," Energies, MDPI, vol. 14(7), pages 1-12, April.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Love, Peter E.D. & Ika, Lavagnon A. & Ahiaga-Dagbui, Dominic D., 2019. "On de-bunking ‘fake news’ in a post truth era: Why does the Planning Fallacy explanation for cost overruns fall short?," Transportation Research Part A: Policy and Practice, Elsevier, vol. 126(C), pages 397-408.
    2. Jenkins, G. & Olasehinde-Williams, G. & Baurzhan, S., 2022. "Is there a net economic loss from employing reference class forecasting in the appraisal of hydropower projects?," Renewable and Sustainable Energy Reviews, Elsevier, vol. 159(C).
    3. Rodolfo Garcia Sierra & Alvaro Zerda Sarmiento, 2016. "Hydropower Megaprojects in Colombia and the Influence of Local Communities: A View from Prospect Theory to Decision Making Process based on Expert Judgment used in Large Organizations," International Journal of Energy Economics and Policy, Econjournals, vol. 6(3), pages 408-420.
    4. Anuja Shaktawat & Shelly Vadhera, 2021. "Risk management of hydropower projects for sustainable development: a review," Environment, Development and Sustainability: A Multidisciplinary Approach to the Theory and Practice of Sustainable Development, Springer, vol. 23(1), pages 45-76, January.
    5. Agnieszka Huterska, 2017. "Public-Private Partnership in Building Sustainable Development of the Kuyavian-Pomeranian Voivodship," European Journal of Interdisciplinary Studies Articles, Revistia Research and Publishing, vol. 3, September.
    6. Servranckx, Tom & Vanhoucke, Mario & Aouam, Tarik, 2021. "Practical application of reference class forecasting for cost and time estimations: Identifying the properties of similarity," European Journal of Operational Research, Elsevier, vol. 295(3), pages 1161-1179.
    7. Miranda Sarmento, J.J., 2014. "Public private partnerships," Other publications TiSEM c7d4c978-234c-4f88-83ed-1, Tilburg University, School of Economics and Management.
    8. Hugo Priemus & Bert van Wee (ed.), 2013. "International Handbook on Mega-Projects," Books, Edward Elgar Publishing, number 14791.
    9. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 0. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 0, pages 1-10.
    10. Ansar, Atif & Flyvbjerg, Bent & Budzier, Alexander & Lunn, Daniel, 2014. "Should we build more large dams? The actual costs of hydropower megaproject development," Energy Policy, Elsevier, vol. 69(C), pages 43-56.
    11. Boeing, Geoff, 2017. "Methods and Measures for Analyzing Complex Street Networks and Urban Form," SocArXiv 93h82, Center for Open Science.
    12. Ayobami Solomon Oyewo & Javier Farfan & Pasi Peltoniemi & Christian Breyer, 2018. "Repercussion of Large Scale Hydro Dam Deployment: The Case of Congo Grand Inga Hydro Project," Energies, MDPI, vol. 11(4), pages 1-30, April.
    13. Ihsan Issa Ahmad Hosani & Fikri T. Dweiri & Udechukwu Ojiako, 2020. "A study of cost overruns in complex multi-stakeholder road projects in the United Arab Emirates," International Journal of System Assurance Engineering and Management, Springer;The Society for Reliability, Engineering Quality and Operations Management (SREQOM),India, and Division of Operation and Maintenance, Lulea University of Technology, Sweden, vol. 11(6), pages 1250-1259, December.
    14. Dejan Makovšek & Marian Moszoro, 2018. "Risk pricing inefficiency in public–private partnerships," Transport Reviews, Taylor & Francis Journals, vol. 38(3), pages 298-321, May.
    15. Kirchherr, Julian & Ahrenshop, Mats-Philip & Charles, Katrina, 2019. "Resettlement lies: Suggestive evidence from 29 large dam projects," World Development, Elsevier, vol. 114(C), pages 208-219.
    16. C. Guccio & G. Pignataro & I. Rizzo, 2012. "Determinants of adaptation costs in procurement: an empirical estimation on Italian public works contracts," Applied Economics, Taylor & Francis Journals, vol. 44(15), pages 1891-1909, May.
    17. Saule Baurzhan & Glenn Jenkins & Godwin O. Olasehinde-Williams, 2021. "The Economic Performance of Hydropower Dams Supported by the World Bank Group, 1975–2015," Working Paper 1463, Economics Department, Queen's University.
    18. Gaudard, Ludovic, 2015. "Pumped-storage project: A short to long term investment analysis including climate change," Renewable and Sustainable Energy Reviews, Elsevier, vol. 49(C), pages 91-99.
    19. Saule Baurzhan & Glenn P. Jenkins & Godwin O. Olasehinde-Williams, 2021. "The Economic Performance of Hydropower Dams Supported by the World Bank Group, 1975–2015," Energies, MDPI, vol. 14(9), pages 1-22, May.
    20. Steininger, Bertram & Groth, Martin & Weber, Birgitte, 2020. "Cost overruns and delays in infrastructure projects: the case of Stuttgart 21," Working Paper Series 20/11, Royal Institute of Technology, Department of Real Estate and Construction Management & Banking and Finance.

    More about this item

    Keywords

    Hydropower; cost uncertainty; investment appraisal; reference class forecasting; Bujagali.;
    All these keywords.

    JEL classification:

    • D81 - Microeconomics - - Information, Knowledge, and Uncertainty - - - Criteria for Decision-Making under Risk and Uncertainty
    • O21 - Economic Development, Innovation, Technological Change, and Growth - - Development Planning and Policy - - - Planning Models; Planning Policy

    NEP fields

    This paper has been announced in the following NEP Reports:

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:qed:dpaper:278. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Mark Babcock (email available below). General contact details of provider: https://edirc.repec.org/data/qedquca.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.