Project scheduling under the threat of catastrophic disruption

Author

Listed:
  • Szmerekovsky, Joseph G.
  • Venkateshan, Prahalad
  • Simonson, Peter D.

Abstract

We consider the case of scheduling a project under the threat of a catastrophic disruption where the likelihood and timing of the disruption are independent of the project schedule and if the disruption occurs, the project is completely canceled. In such scenarios, there is high managerial interest to know the maximum investment at risk at any time during project execution. This can be answered using the alphorn of uncertainty which maps the maximum and minimum possible project costs during project execution when activity durations and, correspondingly, cash flows are random. We prove the NP-hardness of calculating the alphorn of uncertainty and provide a mixed integer linear program for calculating it. The mixed integer linear program is shown to be able to calculate the alphorn for projects with up to 145 activities efficiently. We also show that using railway scheduling as opposed to roadrunner scheduling can significantly reduce the maximum possible investment at risk without significantly delaying the project.

Suggested Citation

  • Szmerekovsky, Joseph G. & Venkateshan, Prahalad & Simonson, Peter D., 2023. "Project scheduling under the threat of catastrophic disruption," European Journal of Operational Research, Elsevier, vol. 309(2), pages 784-794.
  • Handle: RePEc:eee:ejores:v:309:y:2023:i:2:p:784-794
    DOI: 10.1016/j.ejor.2022.12.037
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377221722010049
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ejor.2022.12.037?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Pinker, Edieal & Szmerekovsky, Joseph & Tilson, Vera, 2014. "On the complexity of project scheduling to minimize exposed time," European Journal of Operational Research, Elsevier, vol. 237(2), pages 448-453.
    2. Eli Gutin & Daniel Kuhn & Wolfram Wiesemann, 2015. "Interdiction Games on Markovian PERT Networks," Management Science, INFORMS, vol. 61(5), pages 999-1017, May.
    3. Joseph G. Szmerekovsky & George L. Vairaktarakis, 2006. "Maximizing project cash availability," Naval Research Logistics (NRL), John Wiley & Sons, vol. 53(4), pages 272-284, June.
    4. Creemers, Stefan, 2018. "Maximizing the expected net present value of a project with phase-type distributed activity durations: An efficient globally optimal solution procedure," European Journal of Operational Research, Elsevier, vol. 267(1), pages 16-22.
    5. Wolfram Wiesemann & Daniel Kuhn, 2015. "The Stochastic Time-Constrained Net Present Value Problem," International Handbooks on Information Systems, in: Christoph Schwindt & Jürgen Zimmermann (ed.), Handbook on Project Management and Scheduling Vol. 2, edition 127, chapter 0, pages 753-780, Springer.
    6. Creemers, Stefan & De Reyck, Bert & Leus, Roel, 2015. "Project planning with alternative technologies in uncertain environments," European Journal of Operational Research, Elsevier, vol. 242(2), pages 465-476.
    7. Wendi Tian & Erik Demeulemeester, 2014. "Railway scheduling reduces the expected project makespan over roadrunner scheduling in a multi-mode project scheduling environment," Annals of Operations Research, Springer, vol. 213(1), pages 271-291, February.
    8. Sobel, Matthew J. & Szmerekovsky, Joseph G. & Tilson, Vera, 2009. "Scheduling projects with stochastic activity duration to maximize expected net present value," European Journal of Operational Research, Elsevier, vol. 198(3), pages 697-705, November.
    9. Herroelen, Willy & Leus, Roel, 2004. "The construction of stable project baseline schedules," European Journal of Operational Research, Elsevier, vol. 156(3), pages 550-565, August.
    10. Blazewicz, Jacek & Dror, Moshe & Weglarz, Jan, 1991. "Mathematical programming formulations for machine scheduling: A survey," European Journal of Operational Research, Elsevier, vol. 51(3), pages 283-300, April.
    11. S. Creemers & R. Leus & M. Lambrecht, 2010. "Scheduling Markovian PERT networks to maximize the net present value," Post-Print hal-00800198, HAL.
    12. Van de Vonder, Stijn & Demeulemeester, Erik & Herroelen, Willy, 2008. "Proactive heuristic procedures for robust project scheduling: An experimental analysis," European Journal of Operational Research, Elsevier, vol. 189(3), pages 723-733, September.
    13. Weibo Zheng & Zhengwen He & Nengmin Wang & Tao Jia, 2018. "Proactive and reactive resource-constrained max-NPV project scheduling with random activity duration," Journal of the Operational Research Society, Taylor & Francis Journals, vol. 69(1), pages 115-126, January.
    14. Creemers, Stefan, 2018. "Moments and distribution of the net present value of a serial project," European Journal of Operational Research, Elsevier, vol. 267(3), pages 835-848.
    15. Stefan Creemers, 2018. "Moments and distribution of the net present value of a serial project," Post-Print hal-01914841, HAL.
    16. Vanhoucke, Mario & Coelho, Jose & Debels, Dieter & Maenhout, Broos & Tavares, Luis V., 2008. "An evaluation of the adequacy of project network generators with systematically sampled networks," European Journal of Operational Research, Elsevier, vol. 187(2), pages 511-524, June.
    17. Stefan Creemers & Bert De Reyck & Roel Leus, 2015. "Project planning with alternative technologies in uncertain environments," Post-Print hal-01563008, HAL.
    18. V. G. Kulkarni & V. G. Adlakha, 1986. "Markov and Markov-Regenerative pert Networks," Operations Research, INFORMS, vol. 34(5), pages 769-781, October.
    19. Edieal Pinker & Joseph Szmerekovsky & Vera Tilson, 2013. "Technical Note---Managing a Secret Project," Operations Research, INFORMS, vol. 61(1), pages 65-72, February.
    20. Ted Klastorin & Gary Mitchell, 2013. "Optimal project planning under the threat of a disruptive event," IISE Transactions, Taylor & Francis Journals, vol. 45(1), pages 68-80.
    21. Ben Hermans & Herbert Hamers & Roel Leus & Roy Lindelauf, 2019. "Timely exposure of a secret project: Which activities to monitor?," Naval Research Logistics (NRL), John Wiley & Sons, vol. 66(6), pages 451-468, September.
    22. Stefan Creemers, 2015. "Minimizing the expected makespan of a project with stochastic activity durations under resource constraints," Post-Print hal-02992649, HAL.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Öncü Hazir & Gündüz Ulusoy, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," Post-Print hal-02898162, HAL.
    2. Hazır, Öncü & Ulusoy, Gündüz, 2020. "A classification and review of approaches and methods for modeling uncertainty in projects," International Journal of Production Economics, Elsevier, vol. 223(C).
    3. Hermans, Ben & Leus, Roel & Looy, Bart Van, 2023. "Deciding on scheduling, secrecy, and patenting during the new product development process: The relevance of project planning models," Omega, Elsevier, vol. 116(C).
    4. Creemers, Stefan, 2018. "Maximizing the expected net present value of a project with phase-type distributed activity durations: An efficient globally optimal solution procedure," European Journal of Operational Research, Elsevier, vol. 267(1), pages 16-22.
    5. Stefan Creemers, 2019. "The preemptive stochastic resource-constrained project scheduling problem," Post-Print hal-02992618, HAL.
    6. Creemers, Stefan, 2019. "The preemptive stochastic resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 277(1), pages 238-247.
    7. Creemers, Stefan, 2018. "Moments and distribution of the net present value of a serial project," European Journal of Operational Research, Elsevier, vol. 267(3), pages 835-848.
    8. Morteza Davari & Erik Demeulemeester, 2019. "The proactive and reactive resource-constrained project scheduling problem," Journal of Scheduling, Springer, vol. 22(2), pages 211-237, April.
    9. Alessio Angius & András Horváth & Marcello Urgo, 2021. "A Kronecker Algebra Formulation for Markov Activity Networks with Phase-Type Distributions," Mathematics, MDPI, vol. 9(12), pages 1-22, June.
    10. Salim Rostami & Stefan Creemers & Roel Leus, 2018. "New strategies for stochastic resource-constrained project scheduling," Journal of Scheduling, Springer, vol. 21(3), pages 349-365, June.
    11. Eli Gutin & Daniel Kuhn & Wolfram Wiesemann, 2015. "Interdiction Games on Markovian PERT Networks," Management Science, INFORMS, vol. 61(5), pages 999-1017, May.
    12. Yangyang Liang & Nanfang Cui & Tian Wang & Erik Demeulemeester, 2019. "Robust resource-constrained max-NPV project scheduling with stochastic activity duration," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 41(1), pages 219-254, March.
    13. Xiong, Jian & Leus, Roel & Yang, Zhenyu & Abbass, Hussein A., 2016. "Evolutionary multi-objective resource allocation and scheduling in the Chinese navigation satellite system project," European Journal of Operational Research, Elsevier, vol. 251(2), pages 662-675.
    14. Servranckx, Tom & Vanhoucke, Mario, 2019. "A tabu search procedure for the resource-constrained project scheduling problem with alternative subgraphs," European Journal of Operational Research, Elsevier, vol. 273(3), pages 841-860.
    15. Balouka, Noemie & Cohen, Izack, 2021. "A robust optimization approach for the multi-mode resource-constrained project scheduling problem," European Journal of Operational Research, Elsevier, vol. 291(2), pages 457-470.
    16. Peymankar, Mahboobeh & Davari, Morteza & Ranjbar, Mohammad, 2021. "Maximizing the expected net present value in a project with uncertain cash flows," European Journal of Operational Research, Elsevier, vol. 294(2), pages 442-452.
    17. Creemers, Stefan & De Reyck, Bert & Leus, Roel, 2015. "Project planning with alternative technologies in uncertain environments," European Journal of Operational Research, Elsevier, vol. 242(2), pages 465-476.
    18. Wenhui Zhao & Nicholas G. Hall & Zhixin Liu, 2020. "Project Evaluation and Selection with Task Failures," Production and Operations Management, Production and Operations Management Society, vol. 29(2), pages 428-446, February.
    19. Rostami, Salim & Creemers, Stefan & Wei, Wenchao & Leus, Roel, 2019. "Sequential testing of n-out-of-n systems: Precedence theorems and exact methods," European Journal of Operational Research, Elsevier, vol. 274(3), pages 876-885.
    20. Bruni, M.E. & Di Puglia Pugliese, L. & Beraldi, P. & Guerriero, F., 2017. "An adjustable robust optimization model for the resource-constrained project scheduling problem with uncertain activity durations," Omega, Elsevier, vol. 71(C), pages 66-84.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:309:y:2023:i:2:p:784-794. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.