Optimization-based heuristics for underground mine scheduling

Author

Listed:
  • O’Sullivan, Dónal
  • Newman, Alexandra

Abstract

Underground mine production scheduling possesses mathematical structure similar to and yields many of the same challenges as general scheduling problems. That is, binary variables represent the time at which various activities are scheduled. Typical objectives seek to minimize costs or some measure of production time, or to maximize net present value; two principal types of constraints exist: (i) resource constraints and (ii) precedence constraints. In our setting, we maximize “discounted metal production” for the remaining life of an underground lead and zinc mine that uses three different underground methods to extract the ore. Resource constraints limit the grade, tonnage, and backfill paste (used for structural stability) in each time period, while precedence constraints enforce the sequence in which extraction (and backfill) is performed in accordance with the underground mining methods used. We tailor exact and heuristic approaches to reduce model size, and develop an optimization-based decomposition heuristic; both of these methods transform a computationally intractable problem to one for which we obtain solutions in seconds, or, at most, hours for problem instances based on data sets from the Lisheen mine near Thurles, Ireland.

Suggested Citation

  • O’Sullivan, Dónal & Newman, Alexandra, 2015. "Optimization-based heuristics for underground mine scheduling," European Journal of Operational Research, Elsevier, vol. 241(1), pages 248-259.
  • Handle: RePEc:eee:ejores:v:241:y:2015:i:1:p:248-259
    DOI: 10.1016/j.ejor.2014.08.020
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0377221714006559
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ejor.2014.08.020?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. John J. Bartholdi & James B. Orlin & H. Donald Ratliff, 1980. "Cyclic Scheduling via Integer Programs with Circular Ones," Operations Research, INFORMS, vol. 28(5), pages 1074-1085, October.
    2. Gerald Brown & Joseph Keegan & Brian Vigus & Kevin Wood, 2001. "The Kellogg Company Optimizes Production, Inventory, and Distribution," Interfaces, INFORMS, vol. 31(6), pages 1-15, December.
    3. Martinez, Michael A. & Newman, Alexandra M., 2011. "A solution approach for optimizing long- and short-term production scheduling at LKAB's Kiruna mine," European Journal of Operational Research, Elsevier, vol. 211(1), pages 184-197, May.
    4. Dónal O’Sullivan & Alexandra Newman, 2014. "Extraction and Backfill Scheduling in a Complex Underground Mine," Interfaces, INFORMS, vol. 44(2), pages 204-221, April.
    5. Underwood, Robert & Tolwinski, Boleslaw, 1998. "A mathematical programming viewpoint for solving the ultimate pit problem," European Journal of Operational Research, Elsevier, vol. 107(1), pages 96-107, May.
    6. Alonso-Ayuso, Antonio & Carvallo, Felipe & Escudero, Laureano F. & Guignard, Monique & Pi, Jiaxing & Puranmalka, Raghav & Weintraub, Andrés, 2014. "Medium range optimization of copper extraction planning under uncertainty in future copper prices," European Journal of Operational Research, Elsevier, vol. 233(3), pages 711-726.
    7. W. Matthew Carlyle & B. Curtis Eaves, 2001. "Underground Planning at Stillwater Mining Company," Interfaces, INFORMS, vol. 31(4), pages 50-60, August.
    8. Alexandra M. Newman & Enrique Rubio & Rodrigo Caro & Andrés Weintraub & Kelly Eurek, 2010. "A Review of Operations Research in Mine Planning," Interfaces, INFORMS, vol. 40(3), pages 222-245, June.
    9. Ramazan, Salih, 2007. "The new Fundamental Tree Algorithm for production scheduling of open pit mines," European Journal of Operational Research, Elsevier, vol. 177(2), pages 1153-1166, March.
    10. Newman, Alexandra M. & Kuchta, Mark, 2007. "Using aggregation to optimize long-term production planning at an underground mine," European Journal of Operational Research, Elsevier, vol. 176(2), pages 1205-1218, January.
    11. W. Brian Lambert & Andrea Brickey & Alexandra M. Newman & Kelly Eurek, 2014. "Open-Pit Block-Sequencing Formulations: A Tutorial," Interfaces, INFORMS, vol. 44(2), pages 127-142, April.
    12. Dillenberger, Christof & Escudero, Laureano F. & Wollensak, Artur & Zhang, Wu, 1994. "On practical resource allocation for production planning and scheduling with period overlapping setups," European Journal of Operational Research, Elsevier, vol. 75(2), pages 275-286, June.
    13. Laureano Escudero & Javier Salmeron, 2005. "On a Fix-and-Relax Framework for a Class of Project Scheduling Problems," Annals of Operations Research, Springer, vol. 140(1), pages 163-188, November.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Mousavi, Amin & Sellers, Ewan, 2019. "Optimisation of production planning for an innovative hybrid underground mining method," Resources Policy, Elsevier, vol. 62(C), pages 184-192.
    2. Moreno, Eduardo & Rezakhah, Mojtaba & Newman, Alexandra & Ferreira, Felipe, 2017. "Linear models for stockpiling in open-pit mine production scheduling problems," European Journal of Operational Research, Elsevier, vol. 260(1), pages 212-221.
    3. Chung, Joyce & Asad, Mohammad Waqar Ali & Topal, Erkan, 2022. "Timing of transition from open-pit to underground mining: A simultaneous optimisation model for open-pit and underground mine production schedules," Resources Policy, Elsevier, vol. 77(C).
    4. Morales, Nelson & Mancilla, Diego & Miranda, Roberto & Vallejos, Javier, 2022. "A fast method to develop an optimal operational sublevel stope design," Resources Policy, Elsevier, vol. 77(C).
    5. King, Barry & Goycoolea, Marcos & Newman, A., 2017. "Optimizing the open pit-to-underground mining transition," European Journal of Operational Research, Elsevier, vol. 257(1), pages 297-309.
    6. Ghorbani, Yousef & Nwaila, Glen T. & Zhang, Steven E. & Bourdeau, Julie E. & Cánovas, Manuel & Arzua, Javier & Nikadat, Nooraddin, 2023. "Moving towards deep underground mineral resources: Drivers, challenges and potential solutions," Resources Policy, Elsevier, vol. 80(C).
    7. Chimunhu, Prosper & Topal, Erkan & Ajak, Ajak Duany & Asad, Waqar, 2022. "A review of machine learning applications for underground mine planning and scheduling," Resources Policy, Elsevier, vol. 77(C).

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. King, Barry & Goycoolea, Marcos & Newman, A., 2017. "Optimizing the open pit-to-underground mining transition," European Journal of Operational Research, Elsevier, vol. 257(1), pages 297-309.
    2. Rafael Epstein & Marcel Goic & Andrés Weintraub & Jaime Catalán & Pablo Santibáñez & Rodolfo Urrutia & Raúl Cancino & Sergio Gaete & Augusto Aguayo & Felipe Caro, 2012. "Optimizing Long-Term Production Plans in Underground and Open-Pit Copper Mines," Operations Research, INFORMS, vol. 60(1), pages 4-17, February.
    3. Gonzalo Muñoz & Daniel Espinoza & Marcos Goycoolea & Eduardo Moreno & Maurice Queyranne & Orlando Rivera Letelier, 2018. "A study of the Bienstock–Zuckerberg algorithm: applications in mining and resource constrained project scheduling," Computational Optimization and Applications, Springer, vol. 69(2), pages 501-534, March.
    4. Nesbitt, Peter & Blake, Lewis R. & Lamas, Patricio & Goycoolea, Marcos & Pagnoncelli, Bernardo K. & Newman, Alexandra & Brickey, Andrea, 2021. "Underground mine scheduling under uncertainty," European Journal of Operational Research, Elsevier, vol. 294(1), pages 340-352.
    5. Lorenzo Reus & Mathias Belbèze & Hans Feddersen & Enrique Rubio, 2018. "Extraction Planning Under Capacity Uncertainty at the Chuquicamata Underground Mine," Interfaces, INFORMS, vol. 48(6), pages 543-555, November.
    6. Akshay Chowdu & Peter Nesbitt & Andrea Brickey & Alexandra M. Newman, 2022. "Operations Research in Underground Mine Planning: A Review," Interfaces, INFORMS, vol. 52(2), pages 109-132, March.
    7. Marco Schulze & Julia Rieck & Cinna Seifi & Jürgen Zimmermann, 2016. "Machine scheduling in underground mining: an application in the potash industry," OR Spectrum: Quantitative Approaches in Management, Springer;Gesellschaft für Operations Research e.V., vol. 38(2), pages 365-403, March.
    8. Alexandra M. Newman & Enrique Rubio & Rodrigo Caro & Andrés Weintraub & Kelly Eurek, 2010. "A Review of Operations Research in Mine Planning," Interfaces, INFORMS, vol. 40(3), pages 222-245, June.
    9. Barry King & Alexandra Newman, 2018. "Optimizing the Cutoff Grade for an Operational Underground Mine," Interfaces, INFORMS, vol. 48(4), pages 357-371, August.
    10. Michelle L. Blom & Adrian R. Pearce & Peter J. Stuckey, 2016. "A Decomposition-Based Algorithm for the Scheduling of Open-Pit Networks Over Multiple Time Periods," Management Science, INFORMS, vol. 62(10), pages 3059-3084, October.
    11. Jélvez, Enrique & Morales, Nelson & Nancel-Penard, Pierre & Cornillier, Fabien, 2020. "A new hybrid heuristic algorithm for the Precedence Constrained Production Scheduling Problem: A mining application," Omega, Elsevier, vol. 94(C).
    12. W. Lambert & A. Newman, 2014. "Tailored Lagrangian Relaxation for the open pit block sequencing problem," Annals of Operations Research, Springer, vol. 222(1), pages 419-438, November.
    13. Zeng, Lanyan & Liu, Shi Qiang & Kozan, Erhan & Corry, Paul & Masoud, Mahmoud, 2021. "A comprehensive interdisciplinary review of mine supply chain management," Resources Policy, Elsevier, vol. 74(C).
    14. Dónal O’Sullivan & Alexandra Newman, 2014. "Extraction and Backfill Scheduling in a Complex Underground Mine," Interfaces, INFORMS, vol. 44(2), pages 204-221, April.
    15. Baptista, Susana & Barbosa-Póvoa, Ana Paula & Escudero, Laureano F. & Gomes, Maria Isabel & Pizarro, Celeste, 2019. "On risk management of a two-stage stochastic mixed 0–1 model for the closed-loop supply chain design problem," European Journal of Operational Research, Elsevier, vol. 274(1), pages 91-107.
    16. Martin L. Smith & Stewart J. Wicks, 2014. "Medium-Term Production Scheduling of the Lumwana Mining Complex," Interfaces, INFORMS, vol. 44(2), pages 176-194, April.
    17. Daniel Espinoza & Marcos Goycoolea & Eduardo Moreno & Alexandra Newman, 2013. "MineLib: a library of open pit mining problems," Annals of Operations Research, Springer, vol. 206(1), pages 93-114, July.
    18. Thomas W. M. Vossen & R. Kevin Wood & Alexandra M. Newman, 2016. "Hierarchical Benders Decomposition for Open-Pit Mine Block Sequencing," Operations Research, INFORMS, vol. 64(4), pages 771-793, August.
    19. Zhang, Jian & Nault, Barrie R. & Dimitrakopoulos, Roussos G., 2019. "Optimizing a mineral value chain with market uncertainty using benders decomposition," European Journal of Operational Research, Elsevier, vol. 274(1), pages 227-239.
    20. Siyu Tu & Mingtao Jia & Liguan Wang & Shuzhao Feng & Shuang Huang, 2022. "A Multi-Equipment Task Assignment Model for the Horizontal Stripe Pre-Cut Mining Method," Sustainability, MDPI, vol. 14(24), pages 1-18, December.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:241:y:2015:i:1:p:248-259. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.