Linear programming based approaches for the discrete time/cost trade-off problem in project networks

Author

Listed:
  • A B Hafızoğlu

    (Arizona State University)

  • M Azizoğlu

    (Middle East Technical University)

Abstract

In project management, the activity durations can often be reduced by dedicating additional resources. The Time/Cost Trade-off Problem considers the compromise between the total cost and the project duration. The discrete version of the problem assumes a number of time/cost pairs, called modes, and selects a mode for each activity. In this paper, we consider the Discrete Time/Cost Trade-off Problem. We study the Deadline Problem, that is, the problem of minimizing total cost subject to a deadline on the project duration. To solve the Deadline Problem, we propose optimization and approximation algorithms that are based on the optimal Linear Programming Relaxation solutions. Our computational results from large-sized problem instances reveal the satisfactory behaviour of our algorithms.

Suggested Citation

  • A B Hafızoğlu & M Azizoğlu, 2010. "Linear programming based approaches for the discrete time/cost trade-off problem in project networks," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 61(4), pages 676-685, April.
  • Handle: RePEc:pal:jorsoc:v:61:y:2010:i:4:d:10.1057_jors.2009.20
    DOI: 10.1057/jors.2009.20
    as

    Download full text from publisher

    File URL: http://link.springer.com/10.1057/jors.2009.20
    File Function: Abstract
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: https://libkey.io/10.1057/jors.2009.20?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. Martin Skutella, 1998. "Approximation Algorithms for the Discrete Time-Cost Tradeoff Problem," Mathematics of Operations Research, INFORMS, vol. 23(4), pages 909-929, November.
    2. Prabuddha De & E. James Dunne & Jay B. Ghosh & Charles E. Wells, 1997. "Complexity of the Discrete Time-Cost Tradeoff Problem for Project Networks," Operations Research, INFORMS, vol. 45(2), pages 302-306, April.
    3. Don R. Robinson, 1975. "A Dynamic Programming Solution to Cost-Time Tradeoff for CPM," Management Science, INFORMS, vol. 22(2), pages 158-166, October.
    4. Demeulemeester, Erik L. & Herroelen, Willy S. & Elmaghraby, Salah E., 1996. "Optimal procedures for the discrete time/cost trade-off problem in project networks," European Journal of Operational Research, Elsevier, vol. 88(1), pages 50-68, January.
    5. Elmaghraby, Salah E., 1993. "Resource allocation via dynamic programming in activity networks," European Journal of Operational Research, Elsevier, vol. 64(2), pages 199-215, January.
    6. Steve Phillips, Jr. & Mohamed I. Dessouky, 1977. "Solving the Project Time/Cost Tradeoff Problem Using the Minimal Cut Concept," Management Science, INFORMS, vol. 24(4), pages 393-400, December.
    7. James E. Kelley, 1961. "Critical-Path Planning and Scheduling: Mathematical Basis," Operations Research, INFORMS, vol. 9(3), pages 296-320, June.
    8. D. R. Fulkerson, 1961. "A Network Flow Computation for Project Cost Curves," Management Science, INFORMS, vol. 7(2), pages 167-178, January.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. R L Bregman, 2009. "Preemptive expediting to improve project due date performance," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 60(1), pages 120-129, January.
    2. Bregman, Robert L., 2009. "A heuristic procedure for solving the dynamic probabilistic project expediting problem," European Journal of Operational Research, Elsevier, vol. 192(1), pages 125-137, January.
    3. Akkan, Can & Drexl, Andreas & Kimms, Alf, 2000. "Network decomposition-based lower and upper bounds for the discrete time-cost tradeoff problem," Manuskripte aus den Instituten für Betriebswirtschaftslehre der Universität Kiel 527, Christian-Albrechts-Universität zu Kiel, Institut für Betriebswirtschaftslehre.
    4. Kolisch, R. & Padman, R., 2001. "An integrated survey of deterministic project scheduling," Omega, Elsevier, vol. 29(3), pages 249-272, June.
    5. Brucker, Peter & Drexl, Andreas & Mohring, Rolf & Neumann, Klaus & Pesch, Erwin, 1999. "Resource-constrained project scheduling: Notation, classification, models, and methods," European Journal of Operational Research, Elsevier, vol. 112(1), pages 3-41, January.
    6. M. Vanhoucke, 2007. "An electromagnetic time/cost trade-off optimization in project scheduling," Working Papers of Faculty of Economics and Business Administration, Ghent University, Belgium 07/457, Ghent University, Faculty of Economics and Business Administration.
    7. Vanhoucke, Mario, 2005. "New computational results for the discrete time/cost trade-off problem with time-switch constraints," European Journal of Operational Research, Elsevier, vol. 165(2), pages 359-374, September.
    8. Helena Gaspars, 2006. "A conception of a new algorithm for the project time-cost analysis," Operations Research and Decisions, Wroclaw University of Science and Technology, Faculty of Management, vol. 16(3-4), pages 5-27.
    9. Nicole Megow & Rolf H. Möhring & Jens Schulz, 2011. "Decision Support and Optimization in Shutdown and Turnaround Scheduling," INFORMS Journal on Computing, INFORMS, vol. 23(2), pages 189-204, May.
    10. De, Prabuddha & James Dunne, E. & Ghosh, Jay B. & Wells, Charles E., 1995. "The discrete time-cost tradeoff problem revisited," European Journal of Operational Research, Elsevier, vol. 81(2), pages 225-238, March.
    11. Akkan, Can & Drexl, Andreas & Kimms, Alf, 2005. "Network decomposition-based benchmark results for the discrete time-cost tradeoff problem," European Journal of Operational Research, Elsevier, vol. 165(2), pages 339-358, September.
    12. Marcin Anholcer & Helena Gaspars-Wieloch, 2011. "Efficiency analysis of the Kaufmann and Dezbazeille algorithm for the deadline problem," Operations Research and Decisions, Wroclaw University of Science and Technology, Faculty of Management, vol. 21(1), pages 5-18.
    13. Martin Skutella, 1998. "Approximation Algorithms for the Discrete Time-Cost Tradeoff Problem," Mathematics of Operations Research, INFORMS, vol. 23(4), pages 909-929, November.
    14. Choi, Byung-Cheon & Chung, Jibok, 2014. "Complexity results for the linear time–cost tradeoff problem with multiple milestones and completely ordered jobs," European Journal of Operational Research, Elsevier, vol. 236(1), pages 61-68.
    15. Said, Samer S. & Haouari, Mohamed, 2015. "A hybrid simulation-optimization approach for the robust Discrete Time/Cost Trade-off Problem," Applied Mathematics and Computation, Elsevier, vol. 259(C), pages 628-636.
    16. Jorgensen, Trond & Wallace, Stein W., 2000. "Improving project cost estimation by taking into account managerial flexibility," European Journal of Operational Research, Elsevier, vol. 127(2), pages 239-251, December.
    17. Herroelen, Willy & Leus, Roel, 2004. "The construction of stable project baseline schedules," European Journal of Operational Research, Elsevier, vol. 156(3), pages 550-565, August.
    18. Geng, Zhichao & Yuan, Jinjiang, 2023. "Single-machine scheduling of multiple projects with controllable processing times," European Journal of Operational Research, Elsevier, vol. 308(3), pages 1074-1090.
    19. Eleni Hadjiconstantinou & Evelina Klerides, 2010. "A new path-based cutting plane approach for the discrete time-cost tradeoff problem," Computational Management Science, Springer, vol. 7(3), pages 313-336, July.
    20. Zsolt T. Kosztyán & István Szalkai, 2020. "Multimode resource-constrained project scheduling in flexible projects," Journal of Global Optimization, Springer, vol. 76(1), pages 211-241, January.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:pal:jorsoc:v:61:y:2010:i:4:d:10.1057_jors.2009.20. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.palgrave-journals.com/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.