IDEAS home Printed from https://ideas.repec.org/a/gam/jeners/v16y2022i1p283-d1016447.html
   My bibliography  Save this article

Identifying and Ranking the Root Causes of Schedule Delays in Oil and Gas Pipeline Construction Projects

Author

Listed:
  • Adel Alshibani

    (Construction Engineering & Management Department, King Fahd University of Petroleum and Minerals, Dhahran 34463, Saudi Arabia
    Interdisciplinary Research Center of Construction and Building Materials, King Fahd University of Petroleum and Minerals, Dhahran 34463, Saudi Arabia)

  • Mohammed Julaih

    (Construction Engineering & Management Department, King Fahd University of Petroleum and Minerals, Dhahran 34463, Saudi Arabia)

  • Ahamd Adress

    (Construction Engineering & Management Department, King Fahd University of Petroleum and Minerals, Dhahran 34463, Saudi Arabia)

  • Othman Alshamrani

    (Building Engineering Department, Imam Abdulrahman Bin Faisal University, 2835 King Faisal Road, Dammam 34212, Saudi Arabia)

  • Faris Almaziad

    (Building Engineering Department, Imam Abdulrahman Bin Faisal University, 2835 King Faisal Road, Dammam 34212, Saudi Arabia)

Abstract

Delays in completing the construction of oil and gas projects impact the production, sustainability, reliability, and revenues of the company, which result in market share losses in the long term. This research aimed to determine, evaluate, and rank the root causes of schedule delays in oil and gas pipeline projects in Saudi Arabia. Forty-seven different causes were identified firstly from a wide-ranging literature review and then finalized through conducting interviews with two local experts. These causes were ranked by distributing and analyzing questionnaires on the topic. Client-related materials, delays in materials and equipment delivery, permit approval, delays in subcontractor work, and delays in preparing and approving engineering drawings were found to be the top five major causes affecting oil and gas pipeline construction projects. From the initial analyses, it was observed that an adversarial relationship was apparent as the results indicated that the parties tended to blame each other for the delays. The sub-causes of the initial five causes were identified and root cause analysis was performed. A delay in the material and equipment delivery category had the most weighted sub-causes; hence, it is of high importance to mitigate it. Further recommendations were made for different delay causes.

Suggested Citation

  • Adel Alshibani & Mohammed Julaih & Ahamd Adress & Othman Alshamrani & Faris Almaziad, 2022. "Identifying and Ranking the Root Causes of Schedule Delays in Oil and Gas Pipeline Construction Projects," Energies, MDPI, vol. 16(1), pages 1-22, December.
  • Handle: RePEc:gam:jeners:v:16:y:2022:i:1:p:283-:d:1016447
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/1996-1073/16/1/283/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/1996-1073/16/1/283/
    Download Restriction: no
    ---><---

    References listed on IDEAS

    as
    1. Abdullah Rasheed Alhajri & Adel Alshibani, 2018. "Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia," Energies, MDPI, vol. 11(7), pages 1-18, June.
    2. Behlül Üsdiken & Zeynep Sözen & Hayat Enbiyaoḡlu, 1988. "Strategies and boundaries: Subcontracting in construction," Strategic Management Journal, Wiley Blackwell, vol. 9(6), pages 633-637, November.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Murat Gunduz & Abdulrahman Abu-Hijleh, 2020. "Assessment of Human Productivity Drivers for Construction Labor through Importance Rating and Risk Mapping," Sustainability, MDPI, vol. 12(20), pages 1-18, October.
    2. Herve Kabanda & Alex Romard & Fuze Yurtsever & Anjali Wadhera & Joshua Andrews & Craig Merrett, 2021. "Construction Time Estimation Function for Canadian Utility Scale Power Plants," Energies, MDPI, vol. 14(17), pages 1-16, August.
    3. Mohammad Ajmal Nikjow & Li Liang & Xijing Qi & Samad M. E. Sepasgozar & Nicholas Chileshe, 2021. "Triggers of Delays in International Projects Using Engineering Procurement and Construction Delivery Methods in the Belt and Road Initiative: Case Study of a High-Speed Railway Projects," Sustainability, MDPI, vol. 13(17), pages 1-21, August.
    4. Zeynep Sozen & Olcay Kayahan, 2001. "Correlates of the length of the relationship between main and specialist trade contractors in the construction industry," Construction Management and Economics, Taylor & Francis Journals, vol. 19(2), pages 131-133.
    5. Norhana Danial & Mohd Saidin Misnan, 2022. "Possession of Site: Another Layer of Complexity in Road Construction," Sustainability, MDPI, vol. 14(11), pages 1-20, June.
    6. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2019. "Materials Challenges in Reconstruction of Historical Projects: A Case Study of the Old Riwaq Project," Sustainability, MDPI, vol. 11(17), pages 1-19, August.
    7. Anna Zielińska-Chmielewska & Dobrosława Mruk-Tomczak & Anna Wielicka-Regulska, 2021. "Qualitative Research on Solving Difficulties in Maintaining Continuity of Food Supply Chain on the Meat Market during the COVID-19 Pandemic," Energies, MDPI, vol. 14(18), pages 1-19, September.
    8. Faham Tahmasebinia & Vicheth Song, 2022. "Significant Factors Causing Delay in the Cambodian Construction Industry," Sustainability, MDPI, vol. 14(6), pages 1-24, March.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jeners:v:16:y:2022:i:1:p:283-:d:1016447. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.