Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia

Author

Listed:
  • Abdullah Rasheed Alhajri

    (Construction Engineering and Management, KFUPM, Dhahran 31261, Saudi Arabia)

  • Adel Alshibani

    (Architectural Engineering Department KFUPM, Dhahran 31261, Saudi Arabia)

Abstract

This paper presents a study conducted to identify, assess, rank, and compare the most influencing factors causing schedule delays during the construction phase of petrochemical projects in Saudi Arabia. The methodology followed in this research to achieve the main aims is a combination of the comprehensive review of the literature and the interviewing of a number of local experts, which have resulted in identifying 23 factors. A total of 90 completed responses were gathered from 106 received responses. The study found that the most influencing factors causing schedule delays during the construction of petrochemical projects in Saudi Arabia are “Poor site management and supervision by contractors”; “Conflict between the main contractor and subcontractor”; “Poor planning and scheduling of projects by the contractor”; “Delays in material or equipment delivery”; and followed by “Delays in Handing Over Construction Site to the Contractor”. This paper is original in the sense that the areas of knowledge and practice covered in the identified factors were distributed and not available in one source. The factors are derived from personal interviews with selected project managers, project engineers, construction supervisors, and the others from different positions in the project department and from the relevant literature.

Suggested Citation

  • Abdullah Rasheed Alhajri & Adel Alshibani, 2018. "Critical Factors behind Construction Delay in Petrochemical Projects in Saudi Arabia," Energies, MDPI, vol. 11(7), pages 1-18, June.
  • Handle: RePEc:gam:jeners:v:11:y:2018:i:7:p:1652-:d:154329
    as

    Download full text from publisher

    File URL: https://www.mdpi.com/1996-1073/11/7/1652/pdf
    Download Restriction: no

    File URL: https://www.mdpi.com/1996-1073/11/7/1652/
    Download Restriction: no
    ---><---

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Murat Gunduz & Abdulrahman Abu-Hijleh, 2020. "Assessment of Human Productivity Drivers for Construction Labor through Importance Rating and Risk Mapping," Sustainability, MDPI, vol. 12(20), pages 1-18, October.
    2. Herve Kabanda & Alex Romard & Fuze Yurtsever & Anjali Wadhera & Joshua Andrews & Craig Merrett, 2021. "Construction Time Estimation Function for Canadian Utility Scale Power Plants," Energies, MDPI, vol. 14(17), pages 1-16, August.
    3. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2019. "Materials Challenges in Reconstruction of Historical Projects: A Case Study of the Old Riwaq Project," Sustainability, MDPI, vol. 11(17), pages 1-19, August.
    4. Anna Zielińska-Chmielewska & Dobrosława Mruk-Tomczak & Anna Wielicka-Regulska, 2021. "Qualitative Research on Solving Difficulties in Maintaining Continuity of Food Supply Chain on the Meat Market during the COVID-19 Pandemic," Energies, MDPI, vol. 14(18), pages 1-19, September.
    5. Mohammad Ajmal Nikjow & Li Liang & Xijing Qi & Samad M. E. Sepasgozar & Nicholas Chileshe, 2021. "Triggers of Delays in International Projects Using Engineering Procurement and Construction Delivery Methods in the Belt and Road Initiative: Case Study of a High-Speed Railway Projects," Sustainability, MDPI, vol. 13(17), pages 1-21, August.
    6. Norhana Danial & Mohd Saidin Misnan, 2022. "Possession of Site: Another Layer of Complexity in Road Construction," Sustainability, MDPI, vol. 14(11), pages 1-20, June.
    7. Adel Alshibani & Mohammed Julaih & Ahamd Adress & Othman Alshamrani & Faris Almaziad, 2022. "Identifying and Ranking the Root Causes of Schedule Delays in Oil and Gas Pipeline Construction Projects," Energies, MDPI, vol. 16(1), pages 1-22, December.
    8. Faham Tahmasebinia & Vicheth Song, 2022. "Significant Factors Causing Delay in the Cambodian Construction Industry," Sustainability, MDPI, vol. 14(6), pages 1-24, March.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:gam:jeners:v:11:y:2018:i:7:p:1652-:d:154329. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: MDPI Indexing Manager (email available below). General contact details of provider: https://www.mdpi.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.