Cost benefit analysis to assess modular investment: the case of the New Turin-Lyon Railway

Contents:

Author Info

  • Debernardi, Andrea
  • Grimaldi, Raffaele
  • Beria, Paolo

Abstract

The assessment of infrastructure investments is often affected by inaccuracy in traffic forecasting, optimism bias and overvaluation of expected benefits. In general, even when such misrepresentation is not strategically introduced by proponents to push their projects, valuators and decision makers must cope with the existence of a risk of demand levels below expectations and consequent problem of overinvestment. In this sense, the concept of option value suggests that flexible or reversible projects may have a higher economic net present value compared with rigid schemes characterised by sunk costs. However, conventionally used cost benefit analysis (CBA) is very seldom used to manage such problem due to the complexity of the issue (for example when introducing a complete risk analysis). Moreover, such CBAs are still conceived as a static tool to decide ex-ante about an investment. In this paper we develop a theoretical framework and a practical application of CBA to formally manage such uncertainty and help the decision makers by postponing some decisions to the following running phase. The idea is to assess the project as split into smaller functional sections and bind the construction of a further section to the compliance of a pre-determined “switching rule”. In practical terms, we adapt a normal CBA procedure to manage also the time dimension of time of investments to reallocate risks already in the early design stage of transport infrastructures. The purpose of the paper is twofold. Firstly, we introduce a way to extend conventional CBA methodology to manage the phasing of projects. Secondly, we demonstrate both theoretically (with a simplified model) and practically (with a more complex case study) the positive effect of phasing under certain conditions (limitedness of sunk-costs due to phasing, predominance of capacity problems). By numerically developing the CBA of the Turin – Lyon high speed rail project, we show how to reduce the risk of overestimation of traffic and its positive effect in terms of NPV of the project: if forecasts are optimistic, only the most effective parts of the scheme will be built. If the traffic forecasts are correct, the new infrastructure will be built as a whole in steps and will generate the highest net benefits.

Download Info

If you experience problems downloading a file, check if you have the proper application to view it first. In case of further problems read the IDEAS help page. Note that these files are not on the IDEAS site. Please be patient as the files may be large.
File URL: http://mpra.ub.uni-muenchen.de/30327/
File Function: original version
Download Restriction: no

Bibliographic Info

Paper provided by University Library of Munich, Germany in its series MPRA Paper with number 30327.

as in new window
Length:
Date of creation: 13 Mar 2011
Date of revision:
Handle: RePEc:pra:mprapa:30327

Contact details of provider:
Postal: Schackstr. 4, D-80539 Munich, Germany
Phone: +49-(0)89-2180-2219
Fax: +49-(0)89-2180-3900
Web page: http://mpra.ub.uni-muenchen.de
More information through EDIRC

Related research

Keywords: cost benefit analysis; option value; optimism bias; strategic misrepresentation; benefit shortfall; planning fallacy; forecasting;

Find related papers by JEL classification:

This paper has been announced in the following NEP Reports:

References

References listed on IDEAS
Please report citation or reference errors to , or , if you are the registered author of the cited work, log in to your RePEc Author Service profile, click on "citations" and make appropriate adjustments.:
as in new window
  1. McDonald, Robert & Siegel, Daniel, 1986. "The Value of Waiting to Invest," The Quarterly Journal of Economics, MIT Press, vol. 101(4), pages 707-27, November.
Full references (including those not matched with items on IDEAS)

Citations

Lists

This item is not listed on Wikipedia, on a reading list or among the top items on IDEAS.

Statistics

Access and download statistics

Corrections

When requesting a correction, please mention this item's handle: RePEc:pra:mprapa:30327. See general information about how to correct material in RePEc.

For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: (Ekkehart Schlicht).

If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

If references are entirely missing, you can add them using this form.

If the full references list an item that is present in RePEc, but the system did not link to it, you can help with this form.

If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your profile, as there may be some citations waiting for confirmation.

Please note that corrections may take a couple of weeks to filter through the various RePEc services.