First Results on Resource-Constrained Project Scheduling with Model-Endogenous Decision on the Project Structure

In: Operations Research Proceedings 2012

Author

Listed:
  • Carolin Kellenbrink

    (Leibniz Universität Hannover, Institut für Produktionswirtschaft)

Abstract

In projects with alternative modalities, the jobs that actually have to be implemented are not known beforehand, i.e. the project structure is unknown. However, established formulations of the resource-constrained project scheduling problem (RCPSP) assume the project structure to be given in advance. In this paper, the RCPSP is extended by a model-endogenous decision on the project structure in order to include those alternative modalities. The requirements on the project structure decision problem are explained and it is shown that this problem occurs, e.g., with scheduling the turnaround at airports. As a solution approach aspects of a genetic algorithm are presented.

Suggested Citation

  • Carolin Kellenbrink, 2014. "First Results on Resource-Constrained Project Scheduling with Model-Endogenous Decision on the Project Structure," Operations Research Proceedings, in: Stefan Helber & Michael Breitner & Daniel Rösch & Cornelia Schön & Johann-Matthias Graf von der Schu (ed.), Operations Research Proceedings 2012, edition 127, pages 429-434, Springer.
  • Handle: RePEc:spr:oprchp:978-3-319-00795-3_64
    DOI: 10.1007/978-3-319-00795-3_64
    as

    Download full text from publisher

    To our knowledge, this item is not available for download. To find whether it is available, there are three options:
    1. Check below whether another version of this item is available online.
    2. Check on the provider's web page whether it is in fact available.
    3. Perform a search for a similarly titled item that would be available.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Kellenbrink, Carolin & Helber, Stefan, 2015. "Scheduling resource-constrained projects with a flexible project structure," European Journal of Operational Research, Elsevier, vol. 246(2), pages 379-391.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:spr:oprchp:978-3-319-00795-3_64. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.springer.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.