Delays Factors In Construction Projects Development: The Case Of Klang Valley, Malaysia

Author

Listed:
  • ABDELNASER OMRAN
  • OOI AI LING
  • ABDUL HAMID KADIR PAKIR
  • MAHYUDDIN RAMLI

Abstract

The problem of project delays in construction industry is a global phenomenon; Malaysia is no exceptional. Delays are always considered as costly to all parties involved in the project and very often it will results in dispute, claims, total abandonment and blight the feasibility for project owners and retard the development of construction industry. Therefore, the objectives of this paper are to identify the main causes and contributor to the project delays because delays can be minimized only when their causes are identified. Moreover, it is also aimed to investigate the most critical stage throughout the process of project development pertaining to the project delays as well as to recommend various methods that could be adopted by the construction industry players to mitigate the problems. In order to achieve the said objectives, a total of twenty one factors of delays which was then grouped under owner related, contractor related and consultant related delay factors and ten methods to mitigate the project delays were based on literature review. The structural questionnaires were distributed to the targeted respondents in Klang Valley, Malaysia. The findings from this paper shown that owner’s slow in decision making was perceived to be the most significant factor and main causes to the project delays. All of the respondents claimed that working drawing stage being the most critical stage in governing all of these owner’s related delay factors. Besides that, the contractor is deemed to be the main contributor to the project delays in Malaysia construction industry. It is assumed by all of the respondents that the contractor should be responsible for any delays at the construction stage which is considered as the most critical stage in governing the project delays. In order to mitigate the project delays, awarding bids to the right and experience contractor was suggested to be the utmost effective solution in resolving those contractor’s related delay factors.

Suggested Citation

  • Abdelnaser Omran & Ooi Ai Ling & Abdul Hamid Kadir Pakir & Mahyuddin Ramli, 2010. "Delays Factors In Construction Projects Development: The Case Of Klang Valley, Malaysia," Journal of Academic Research in Economics, Spiru Haret University, Faculty of Accounting and Financial Management Constanta, vol. 2(2 (Novemb), pages 135-158.
  • Handle: RePEc:shc:jaresh:v:2:y:2010:i:2:p:135-158
    as

    Download full text from publisher

    File URL: http://www.jare-sh.com/downloads/abstract_nov_2010/omran.pdf
    Download Restriction: no
    ---><---

    More about this item

    Keywords

    CSFs; Project delay; construction industry; construction project development; mitigates delays; Malaysia;
    All these keywords.

    JEL classification:

    • O15 - Economic Development, Innovation, Technological Change, and Growth - - Economic Development - - - Economic Development: Human Resources; Human Development; Income Distribution; Migration
    • M12 - Business Administration and Business Economics; Marketing; Accounting; Personnel Economics - - Business Administration - - - Personnel Management; Executives; Executive Compensation

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:shc:jaresh:v:2:y:2010:i:2:p:135-158. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Claudiu Chiru (email available below). General contact details of provider: https://edirc.repec.org/data/fcuspro.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.