Working Paper 55 - Strategic Considerations for Building a Healthy Pipeline for Bank Group Operations

Author

Listed:

Abstract

The African Development Bank has, since 1982, experienced a problem withbunching of projects towards the fourth quarter of each year’s Lending Program.Contributing factors include both systemic and endogenous constraints as well asexogenous constraints. This paper proposes a holistic approach, that recognizesall the forces at work in the development of Public Investment Programs (PIPs) atthe RMC level as well as the Bank’s internal processes that help to guide andgenerate the pipeline.At the RMC level, the paper examines the need to build the capacity of NationalPlanning Commissions (NPCs) to administer the PIP process. It also advocatesfor sensitizing RMCs, through intensive and persistent dialogue, to decentralize thePIP process in order to minimize the risk of marginalizing the poor and vulnerablegroups of society in the PIP process.At the Bank Group level, the paper examines the existing processes for bothlending and non-lending services and explores areas where the Bank’s lendingoperations need to be streamlined to enhance efficiency and cost-effectiveness.To this end, the need to promote and reward good Economic and Sector Work(ESW) is highlighted along with the need to formalize Country Teams and strengthentheir roles. Furthermore, the concept of a Task Manager (TM) is re-examined andproposals are made that will assure greater responsibility and accountability ofTMs and allow them to play a leadership role in building up the Bank’s pipeline. Amore objective and easily monitorable classification of “bankable” projects isproposed along with a more flexible set of lending instruments that are necessaryto secure a smoother implementation of the Bank’s pipeline beyond the three-yearplanning horizon engendered by the three-year lending cycle.

Suggested Citation

  • Samuel O Onwona, 2002. "Working Paper 55 - Strategic Considerations for Building a Healthy Pipeline for Bank Group Operations," Working Paper Series 189, African Development Bank.
  • Handle: RePEc:adb:adbwps:189
    as

    Download full text from publisher

    File URL: https://www.afdb.org/fileadmin/uploads/afdb/Documents/Publications/00157644-EN-ERP-55.PDF
    Download Restriction: no
    ---><---

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:adb:adbwps:189. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Adeleke Oluwole Salami (email available below). General contact details of provider: https://edirc.repec.org/data/afdbgci.html .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.