Drivers of cost and time overruns: A client and contractor perspective

Author

Listed:
  • Dahlin Peter

    (Mälardalen University, School of Business, Society and Engineering, P.O. Box 883, SE-721 23, Västerås, Sweden.)

  • Pesämaa Ossi

    (Luleå University of Technology, Department of Business Administration, Technology and Social Sciences, SE-971 87, Luleå, Sweden)

Abstract

Large infrastructure investments are expected to be of sustained value to society for a long time. Such investment projects include, for instance, hospitals, tunnels, sport arenas, power plants, roads, railways, and bridges. They involve a complex organization of contracts and agreements. The client is expected to plan, procure, and determine the critical steps of a project, while the contractor should solve issues raised by the client. Many of these agreements are path-dependent and reflect past routines, experiences, and contacts. As such, many investments tend to return to similar sources instead of replacing routines and collaborations that did not work. This can cause change orders that furthermore reflect consequences such as cost and time overruns. While much is known about these effects in construction projects, this paper sheds light on the drivers of change orders. We build upon a sample of 234 observations responding to a survey on investment planning. The results show that project assumptions are often wrong and inadequate in large investments. Such wrong assumptions are caused by interpersonal and leadership issues, poor planning, or sometimes even intentional profit-seeking. Our results show that clients and contractors have different perceptions and enter contractual obligations differently. The implication is, therefore, that better routines of documentation, more frequent feedback, and more accurate or precise standards may close the gap between planning and what is actually achieved. More precise contractual agreements may also create a better process to procure, manage projects, and allocate resources.

Suggested Citation

  • Dahlin Peter & Pesämaa Ossi, 2021. "Drivers of cost and time overruns: A client and contractor perspective," Organization, Technology and Management in Construction, Sciendo, vol. 13(1), pages 2374-2382, January.
  • Handle: RePEc:vrs:otamic:v:13:y:2021:i:1:p:2374-2382:n:2
    DOI: 10.2478/otmcj-2021-0006
    as

    Download full text from publisher

    File URL: https://doi.org/10.2478/otmcj-2021-0006
    Download Restriction: no

    File URL: https://libkey.io/10.2478/otmcj-2021-0006?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:vrs:otamic:v:13:y:2021:i:1:p:2374-2382:n:2. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Peter Golla (email available below). General contact details of provider: https://www.sciendo.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.