IDEAS home Printed from https://ideas.repec.org/a/vrs/bjrecm/v5y2017i1p101-117n8.html
   My bibliography  Save this article

Review of Various Delay Causing Factors and Their Resolution by Application of Lean Principles in India

Author

Listed:
  • Deep Shumank

    (School of Architecture and Built Environment, University of Newcastle, Callaghan 2308 NSW, Australia)

  • Asim Mohd
  • Khan Mohd Kashif

    (Department of Civil Engineering, Integral University, P.O Bas-ha Dasauli Kursi Road Lucknow 226026 UP, India)

Abstract

Practically speaking, not all real estate construction projects are accomplished in the defined span and within budget. Various factors responsible for occurrence of delays are one of the long-standing issues in the field of real estate. Delays make contractors endure productivity loss, cause high disturbance expenses, and prolongation costs. The aim of the research is to summarize several delay causing factors, which are observed in the execution of previous real estate construction projects. It then proposes implementation of standard prevention procedures to minimize delays. Time effect examination is the approach to evaluating and allotting the upshots of delays or changing a venture schedule. This review sets execution framework of the two sub-principles of the Toyota Way attributes known as philosophy sub-principles and process subprinciples to guide real estate construction businesses in their lean change to delay free real estate construction work. These are implemented after investigating the critical factors responsible for delays in the delayed projects by comparing their as-planned schedules with the adjusted schedules. Methods used in the research include structured surveys and content analysis, which is performed after collection of quantitative data from the respondents. The lean construction principles will be designed and provided to clients to be productive in performing work packages on their scheduled time with minimum possibility of time overrun.

Suggested Citation

  • Deep Shumank & Asim Mohd & Khan Mohd Kashif, 2017. "Review of Various Delay Causing Factors and Their Resolution by Application of Lean Principles in India," Baltic Journal of Real Estate Economics and Construction Management, Sciendo, vol. 5(1), pages 101-117, November.
  • Handle: RePEc:vrs:bjrecm:v:5:y:2017:i:1:p:101-117:n:8
    DOI: 10.1515/bjreecm-2017-0008
    as

    Download full text from publisher

    File URL: https://doi.org/10.1515/bjreecm-2017-0008
    Download Restriction: no

    File URL: https://libkey.io/10.1515/bjreecm-2017-0008?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    References listed on IDEAS

    as
    1. Mohammed Al-Khalil & Mohammed Al-Ghafly, 1999. "Important causes of delay in public utility projects in Saudi Arabia," Construction Management and Economics, Taylor & Francis Journals, vol. 17(5), pages 647-655.
    Full references (including those not matched with items on IDEAS)

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2018. "Delay Factors in Reconstruction Projects: A Case Study of Mataf Expansion Project," Sustainability, MDPI, vol. 10(12), pages 1-18, December.
    2. Herve Kabanda & Alex Romard & Fuze Yurtsever & Anjali Wadhera & Joshua Andrews & Craig Merrett, 2021. "Construction Time Estimation Function for Canadian Utility Scale Power Plants," Energies, MDPI, vol. 14(17), pages 1-16, August.
    3. Mohammad Ajmal Nikjow & Li Liang & Xijing Qi & Samad M. E. Sepasgozar & Nicholas Chileshe, 2021. "Triggers of Delays in International Projects Using Engineering Procurement and Construction Delivery Methods in the Belt and Road Initiative: Case Study of a High-Speed Railway Projects," Sustainability, MDPI, vol. 13(17), pages 1-21, August.
    4. Weddy Bernadi Sudirman & Sarwono Hardjomuljadi, 2011. "Project Risk Management in Hydropower Plant Projects," Journal of Infrastructure Development, India Development Foundation, vol. 3(2), pages 171-186, December.
    5. Tirataci Hakan & Yaman Hakan, 2023. "Estimation of ideal construction duration in tender preparation stage for housing projects," Organization, Technology and Management in Construction, Sciendo, vol. 15(1), pages 192-212, January.
    6. Ihab Hijazi & Umit Isikdag & Mohammed Abunemeh & Xin Li & Mariam Hashash & Rani El Meouche & Sergen Cansiz, 2018. "Mapping the Processes of Donor-Funded Construction Projects," Sustainability, MDPI, vol. 10(7), pages 1-25, July.
    7. Basem Al Khatib & Yap Soon Poh & Ahmed El-Shafie, 2020. "Delay Factors Management and Ranking for Reconstruction and Rehabilitation Projects Based on the Relative Importance Index (RII)," Sustainability, MDPI, vol. 12(15), pages 1-21, July.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:vrs:bjrecm:v:5:y:2017:i:1:p:101-117:n:8. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Peter Golla (email available below). General contact details of provider: https://www.sciendo.com .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.