IDEAS home Printed from https://ideas.repec.org/a/pal/jorsoc/v64y2013i8p1106-1117.html
   My bibliography  Save this article

Dynamic priority rule-based forward-backward heuristic algorithm for resource levelling problem in construction project

Author

Listed:
  • Lihua He

    (1] Tianjin University, Tianjin, PR China[2] China University of Petroleum, Qingdao City, PR China)

  • Lianying Zhang

    (Tianjin University, Tianjin, PR China)

Abstract

Resource levelling aims at minimizing the fluctuation of resource usage, which is accomplished by shifting non-critical activities within their float according to some heuristic rules. Most of these rules adopted a unidirectional scheduling based on a static priority rule. In this paper, we propose a dynamic priority rule-based forward-backward heuristic algorithm (FBHA). The FBHA optimizes resource allocation by shifting non-critical activities within their forward free float (FFF), forward total float (FTF) and backward free float (BFF), successively. A project is divided into several phases during each forward/backward scheduling module. In each phase, the shifting sequence and days of non-critical activities depend on a dynamic priority rule set. The FBHA is integrated into the Microsoft Project 2007 commercial software package to improve the performance of the software and facilitate the project planners. One example is analysed to illustrate the iteration process of the proposed FBHA. Another example with multiple precedence constraints is used to demonstrate the effectiveness of the proposed FBHA in complicated construction projects.

Suggested Citation

  • Lihua He & Lianying Zhang, 2013. "Dynamic priority rule-based forward-backward heuristic algorithm for resource levelling problem in construction project," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 64(8), pages 1106-1117, August.
  • Handle: RePEc:pal:jorsoc:v:64:y:2013:i:8:p:1106-1117
    as

    Download full text from publisher

    File URL: http://www.palgrave-journals.com/jors/journal/v64/n8/pdf/jors201333a.pdf
    File Function: Link to full text PDF
    Download Restriction: Access to full text is restricted to subscribers.

    File URL: http://www.palgrave-journals.com/jors/journal/v64/n8/full/jors201333a.html
    File Function: Link to full text HTML
    Download Restriction: Access to full text is restricted to subscribers.
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Boda Liu & Bin Yang & Jianzhuang Xiao & Dayu Zhu & Binghan Zhang & Zhichen Wang & Miaosi Dong, 2021. "Review of Optimization Dynamically Applied in the Construction and the Application Potential of ICT," Sustainability, MDPI, vol. 13(10), pages 1-18, May.
    2. Hongbo Li & Linwen Zheng & Hanyu Zhu, 2023. "Resource leveling in projects with flexible structures," Annals of Operations Research, Springer, vol. 321(1), pages 311-342, February.
    3. Borna Dasović & Mario Galić & Uroš Klanšek, 2020. "A Survey on Integration of Optimization and Project Management Tools for Sustainable Construction Scheduling," Sustainability, MDPI, vol. 12(8), pages 1-18, April.
    4. Yuvraj Gajpal & Ashraf Elazouni, 2015. "Enhanced heuristic for finance-based scheduling of construction projects," Construction Management and Economics, Taylor & Francis Journals, vol. 33(7), pages 531-553, July.

    More about this item

    Statistics

    Access and download statistics

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:pal:jorsoc:v:64:y:2013:i:8:p:1106-1117. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    We have no bibliographic references for this item. You can help adding them by using this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Sonal Shukla or Springer Nature Abstracting and Indexing (email available below). General contact details of provider: http://www.palgrave-journals.com/ .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.