Practical application of reference class forecasting for cost and time estimations: Identifying the properties of similarity
Author
Abstract
Suggested Citation
DOI: 10.1016/j.ejor.2021.03.063
Download full text from publisher
As the access to this document is restricted, you may want to search for a different version of it.
References listed on IDEAS
- Cui, Nanfang & Demeulemeester, Erik & Bie, Li, 2016. "Incorporation of activity sensitivity measures into buffer management to manage project schedule riskAuthor-Name: Hu, Xuejun," European Journal of Operational Research, Elsevier, vol. 249(2), pages 717-727.
- Daniel Kahneman & Dan Lovallo, 1993. "Timid Choices and Bold Forecasts: A Cognitive Perspective on Risk Taking," Management Science, INFORMS, vol. 39(1), pages 17-31, January.
- Cantarelli, C.C. & Molin, E.J.E. & van Wee, B. & Flyvbjerg, B., 2012.
"Characteristics of cost overruns for Dutch transport infrastructure projects and the importance of the decision to build and project phases,"
Transport Policy, Elsevier, vol. 22(C), pages 49-56.
- Chantal C. Cantarelli & Eric J. E. Molin & Bert van Wee & Bent Flyvbjerg, 2013. "Characteristics of Cost Overruns for Dutch Transport Infrastructure Projects and the Importance of the Decision to Build and Project Phases," Papers 1307.2178, arXiv.org, revised Jan 2015.
- Ravi Kumar, P. & Ravi, V., 2007. "Bankruptcy prediction in banks and firms via statistical and intelligent techniques - A review," European Journal of Operational Research, Elsevier, vol. 180(1), pages 1-28, July.
- Cantarelli, C.C. & Flyvbjerg, B. & Buhl, S.L., 2012.
"Geographical variation in project cost performance: the Netherlands versus worldwide,"
Journal of Transport Geography, Elsevier, vol. 24(C), pages 324-331.
- Chantal C. Cantarelli & Bent Flyvbjerg & S{o}ren L. Buhl, 2013. "Geographical Variation in Project Cost Performance: The Netherlands versus Worldwide," Papers 1307.2181, arXiv.org.
- Daniel Kahneman & Amos Tversky, 2013.
"Prospect Theory: An Analysis of Decision Under Risk,"
World Scientific Book Chapters, in: Leonard C MacLean & William T Ziemba (ed.), HANDBOOK OF THE FUNDAMENTALS OF FINANCIAL DECISION MAKING Part I, chapter 6, pages 99-127,
World Scientific Publishing Co. Pte. Ltd..
- Kahneman, Daniel & Tversky, Amos, 1979. "Prospect Theory: An Analysis of Decision under Risk," Econometrica, Econometric Society, vol. 47(2), pages 263-291, March.
- Amos Tversky & Daniel Kahneman, 1979. "Prospect Theory: An Analysis of Decision under Risk," Levine's Working Paper Archive 7656, David K. Levine.
- Renata Walczak & Tomasz Majchrzak, 2018. "Implementation Of The Reference Class Forecasting Method For Projects Implemented In A Chemical Industry Company," Acta Oeconomica Pragensia, Prague University of Economics and Business, vol. 2018(1), pages 25-33.
- Bent Flyvbjerg, 2007.
"Policy and Planning for Large-Infrastructure Projects: Problems, Causes, Cures,"
Environment and Planning B, , vol. 34(4), pages 578-597, August.
- Flyvbjerg, Bent, 2005. "Policy and planning for large infrastructure projects : problems, causes, cures," Policy Research Working Paper Series 3781, The World Bank.
- Bent Flyvbjerg, 2013. "Policy and Planning for Large Infrastructure Projects: Problems, Causes, Cures," Papers 1303.7400, arXiv.org.
- Vanhoucke, Mario & Coelho, Jose & Debels, Dieter & Maenhout, Broos & Tavares, Luis V., 2008. "An evaluation of the adequacy of project network generators with systematically sampled networks," European Journal of Operational Research, Elsevier, vol. 187(2), pages 511-524, June.
- Cantarelli, C.C. & van Wee, B. & Molin, E.J.E. & Flyvbjerg, B., 2012. "Different cost performance: different determinants?," Transport Policy, Elsevier, vol. 22(C), pages 88-95.
- Wauters, Mathieu & Vanhoucke, Mario, 2017. "A Nearest Neighbour extension to project duration forecasting with Artificial Intelligence," European Journal of Operational Research, Elsevier, vol. 259(3), pages 1097-1111.
- Odeck, James, 2004. "Cost overruns in road construction--what are their sizes and determinants?," Transport Policy, Elsevier, vol. 11(1), pages 43-53, January.
- Nikolopoulos, K. & Goodwin, P. & Patelis, A. & Assimakopoulos, V., 2007. "Forecasting with cue information: A comparison of multiple regression with alternative forecasting approaches," European Journal of Operational Research, Elsevier, vol. 180(1), pages 354-368, July.
- Noreen, Eric, 1988. "The economics of ethics: A new perspective on agency theory," Accounting, Organizations and Society, Elsevier, vol. 13(4), pages 359-369, June.
- Valadares Tavares, L. & Antunes Ferreira, J. & Silva Coelho, J., 1999. "The risk of delay of a project in terms of the morphology of its network," European Journal of Operational Research, Elsevier, vol. 119(2), pages 510-537, December.
- Madadi, M. & Iranmanesh, H., 2012. "A management oriented approach to reduce a project duration and its risk (variability)," European Journal of Operational Research, Elsevier, vol. 219(3), pages 751-761.
Citations
Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
Cited by:
- Lordan-Perret, Rebecca & Bärenbold, Rebekka & Weigt, Hannes & Rosner, Robert, 2023.
"An ex-ante method to verify commercial U.S. nuclear power plant decommissioning cost estimates,"
Energy Economics, Elsevier, vol. 127(PB).
- Lordan-Perret, Rebecca & Bärenbold, Rebekka & Weigt, Hannes & Rosner, Robert, 2022. "An Ex-Ante Method to Verify Commercial U.S. Nuclear Power Plant Decommissioning Cost Estimates," Working papers 2022/08, Faculty of Business and Economics - University of Basel.
- Dorota Kuchta & Paolo Canonico & Vincenza Capone & Guido Capaldo, 2023. "Uncertainty in the Planning Phase of Public Projects—Its Scope, Consequences, and Possible Remedies," Administrative Sciences, MDPI, vol. 13(6), pages 1-17, June.
- Ünsal-Altuncan, Izel & Vanhoucke, Mario, 2024. "A hybrid forecasting model to predict the duration and cost performance of projects with Bayesian Networks," European Journal of Operational Research, Elsevier, vol. 315(2), pages 511-527.
Most related items
These are the items that most often cite the same works as this one and are cited by the same works as this one.- Cavalieri, Marina & Cristaudo, Rossana & Guccio, Calogero, 2019. "On the magnitude of cost overruns throughout the project life-cycle: An assessment for the Italian transport infrastructure projects," Transport Policy, Elsevier, vol. 79(C), pages 21-36.
- Dejan Makovšek & Marian Moszoro, 2018.
"Risk pricing inefficiency in public–private partnerships,"
Transport Reviews, Taylor & Francis Journals, vol. 38(3), pages 298-321, May.
- Makovsek, Dejan & Moszoro, Marian W., 2017. "Risk pricing inefficiency in public-private partnerships," MPRA Paper 101574, University Library of Munich, Germany.
- Steininger, Bertram & Groth, Martin & Weber, Birgitte, 2020. "Cost overruns and delays in infrastructure projects: the case of Stuttgart 21," Working Paper Series 20/11, Royal Institute of Technology, Department of Real Estate and Construction Management & Banking and Finance.
- Verweij, Stefan & van Meerkerk, Ingmar & Korthagen, Iris A., 2015. "Reasons for contract changes in implementing Dutch transportation infrastructure projects: An empirical exploration," Transport Policy, Elsevier, vol. 37(C), pages 195-202.
- Love, Peter E.D. & Ahiaga-Dagbui, Dominic D. & Irani, Zahir, 2016. "Cost overruns in transportation infrastructure projects: Sowing the seeds for a probabilistic theory of causation," Transportation Research Part A: Policy and Practice, Elsevier, vol. 92(C), pages 184-194.
- Miranda Sarmento, J.J., 2014. "Public private partnerships," Other publications TiSEM c7d4c978-234c-4f88-83ed-1, Tilburg University, School of Economics and Management.
- Makovšek, Dejan, 2014. "Systematic construction risk, cost estimation mechanism and unit price movements," Transport Policy, Elsevier, vol. 35(C), pages 135-145.
- Odeck, James, 2014. "Do reforms reduce the magnitudes of cost overruns in road projects? Statistical evidence from Norway," Transportation Research Part A: Policy and Practice, Elsevier, vol. 65(C), pages 68-79.
- Love, Peter E.D. & Zhou, Jingyang & Edwards, David J. & Irani, Zahir & Sing, Chun-Pong, 2017. "Off the rails: The cost performance of infrastructure rail projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 99(C), pages 14-29.
- Chong, Uven & Hopkins, Omar, 2016. "An international experience on the evolution of road costs during the project life cycle," Transport Policy, Elsevier, vol. 48(C), pages 60-66.
- Wasiu Olayinka FAWOLE & Burhan ÖZKAN, 2017. "Identifying the Drivers of Food Security Based on Perception among Households in South Western Nigeria," European Journal of Interdisciplinary Studies Articles, Revistia Research and Publishing, vol. 3, ejis_v3_i.
- Flyvbjerg, Bent & Ansar, Atif & Budzier, Alexander & Buhl, Søren & Cantarelli, Chantal & Garbuio, Massimo & Glenting, Carsten & Holm, Mette Skamris & Lovallo, Dan & Lunn, Daniel & Molin, Eric & Rønnes, 2018. "Five things you should know about cost overrun," Transportation Research Part A: Policy and Practice, Elsevier, vol. 118(C), pages 174-190.
- Love, Peter E.D. & Ahiaga-Dagbui, Dominic D., 2018. "Debunking fake news in a post-truth era: The plausible untruths of cost underestimation in transport infrastructure projects," Transportation Research Part A: Policy and Practice, Elsevier, vol. 113(C), pages 357-368.
- Hugo Priemus & Bert van Wee (ed.), 2013. "International Handbook on Mega-Projects," Books, Edward Elgar Publishing, number 14791.
- Petter Osmundsen & Kristin Helen Roll, 2016.
"Rig Rates and Drilling Speed: Reinforcing Effects,"
CESifo Working Paper Series
5895, CESifo.
- Osmundsen, Petter & Roll, Kristin Helen, 2016. "Rig rates and drilling speed: reinforcing effects," UiS Working Papers in Economics and Finance 2016/4, University of Stavanger.
- Abeysekara, Baudhi & Perera, Piyaruwan & Chhipi Shrestha, Gyan Kumar & Gunaruwan, Lalithasiri & Kumarage, Amal & Sadiq, Rehan & Hewage, Kasun, 2021. "Improving the capital deployment efficiency: An infrastructure investment planning process in transportation project," Research in Transportation Economics, Elsevier, vol. 88(C).
- Awojobi, Omotola & Jenkins, Glenn P., 2016.
"Managing the cost overrun risks of hydroelectric dams: An application of reference class forecasting techniques,"
Renewable and Sustainable Energy Reviews, Elsevier, vol. 63(C), pages 19-32.
- Omotola Awojobi & Glenn P. Jenkins, 2015. "Managing the Cost Overrun Risks of Hydroelectric Dams: An Application of Reference Class Forecasting Techniques," Development Discussion Papers 2015-06, JDI Executive Programs.
- Wauters, Mathieu & Vanhoucke, Mario, 2017. "A Nearest Neighbour extension to project duration forecasting with Artificial Intelligence," European Journal of Operational Research, Elsevier, vol. 259(3), pages 1097-1111.
- Miranda Sarmento, J.J. & Renneboog, Luc, 2017. "Cost overruns in public sector investment projects," Other publications TiSEM 51799a3e-4c78-4dbd-b330-b, Tilburg University, School of Economics and Management.
- Francisco Pinheiro Catalão & Carlos Oliveira Cruz & Joaquim Miranda Sarmento, 2023. "The entanglement of time and cost deviations in public projects," Annals of Public and Cooperative Economics, Wiley Blackwell, vol. 94(1), pages 241-272, March.
More about this item
Keywords
Project management; Project forecasting; Reference class forecasting; Real project data; Project similarity;All these keywords.
Statistics
Access and download statisticsCorrections
All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:ejores:v:295:y:2021:i:3:p:1161-1179. See general information about how to correct material in RePEc.
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.
For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/eor .
Please note that corrections may take a couple of weeks to filter through the various RePEc services.