Time slack-based techniques for robust project scheduling subject to resource uncertainty

Contents:

Author Info

  • Lambrechts, Olivier
  • Demeulemeester, Erik
  • Herroelen, Willy
Registered author(s):

    Abstract

    The resource-constrained project scheduling problem (RCPSP) has been the subject of a great deal of research during the previous decades. This is not surprising given the high practical relevance of this scheduling problem. Nevertheless, extensions are needed to be able to cope with situations arising in practice such as multiple activity execution modes, activity duration changes and resource breakdowns. In this paper we analytically determine the impact of unexpected resource breakdowns on activity durations. Furthermore, using this information we develop an approach for inserting explicit idle time into the project schedule in order to protect it as well as possible from disruptions caused by resource unavailabilities. This strategy will be compared to a traditional simulation-based procedure and to a heuristic developed for the case of stochastic activity durations.

    Download Info

    If you experience problems downloading a file, check if you have the proper application to view it first. In case of further problems read the IDEAS help page. Note that these files are not on the IDEAS site. Please be patient as the files may be large.
    File URL: https://lirias.kuleuven.be/bitstream/123456789/272147/3/fulltext.pdf
    Our checks indicate that this address may not be valid because: 400 Bad Request. If this is indeed the case, please notify (Carl Demeyere)
    Download Restriction: no

    Bibliographic Info

    Paper provided by Katholieke Universiteit Leuven in its series Open Access publications from Katholieke Universiteit Leuven with number urn:hdl:123456789/272147.

    as in new window
    Length:
    Date of creation: 2011
    Date of revision:
    Publication status: Published in Annals of Operations Research (2011) v.186, p.443-464
    Handle: RePEc:ner:leuven:urn:hdl:123456789/272147

    Contact details of provider:
    Web page: http://www.kuleuven.be

    Related research

    Keywords: Robust scheduling; Project scheduling; Resource breakdowns; Proactive; Time buffering;

    This paper has been announced in the following NEP Reports:

    References

    No references listed on IDEAS
    You can help add them by filling out this form.

    Citations

    Lists

    This item is not listed on Wikipedia, on a reading list or among the top items on IDEAS.

    Statistics

    Access and download statistics

    Corrections

    When requesting a correction, please mention this item's handle: RePEc:ner:leuven:urn:hdl:123456789/272147

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: (Carl Demeyere).

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If references are entirely missing, you can add them using this form.

    If the full references list an item that is present in RePEc, but the system did not link to it, you can help with this form.

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your profile, as there may be some citations waiting for confirmation.

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.