Capacity Factor Risk At Nuclear Power Plants
Abstract
We develop a model of the dynamic structure of capacity factor risk. It incorporates the risk that the capacity factor may vary widely from year-to-year, and also the risk that the reactor may be permanently shutdown prior to the end of its anticipated useful life. We then fit the parameters of the model to the IAEA’s PRIS dataset of historical capacity factors on reactors across the globe. The estimated capacity factor risk is greatest in the first year of operation. It then quickly declines over the next couple of years, after which it is approximately constant. Whether risk is constant or increasing in later years depends significantly on the probability of a premature permanent shutdown of the reactor. Because these should be very rare events, the probability is difficult to estimate reliably from the small historical sample of observations. Our base case is parameterized with a conservatively low probability of a premature permanent shutdown which yields the approximately constant variance. Our model, combined with the global historical dataset, also yields relatively low estimates for the expected level of the capacity factor through the life of the plant. Our base case estimate is approximately 74%. Focusing on alternative subsets of the data raises the estimated mean capacity factor marginally, but not significantly, unless the sample chosen is restricted to selected countries over select years. This emphasizes the need for judgment in exploiting the historical data to project future probabilities.Download Info
If you experience problems downloading a file, check if you have the proper application to view it first. In case of further problems read the IDEAS help page. Note that these files are not on the IDEAS site. Please be patient as the files may be large.Bibliographic Info
Paper provided by Massachusetts Institute of Technology, Center for Energy and Environmental Policy Research in its series Working Papers with number 1016.Length:
Date of creation: Nov 2010
Date of revision:
Handle: RePEc:mee:wpaper:1016
Contact details of provider:
Postal: 77 Massachusetts Ave. (Building E40-279), Cambridge, MA 02139-4307
Phone: (617) 253-3551
Fax: (617) 253-9845
Email:
Web page: http://tisiphone.mit.edu/RePEc
More information through EDIRC
Related research
Keywords:This paper has been announced in the following NEP Reports:
- NEP-ALL-2010-12-23 (All new papers)
- NEP-ENE-2010-12-23 (Energy Economics)
References
References listed on IDEASPlease report citation or reference errors to , or , if you are the registered author of the cited work, log in to your RePEc Author Service profile, click on "citations" and make appropriate adjustments.:
- Geoffrey Rothwell, 2006. "A Real Options Approach to Evaluating New Nuclear Power Plants," The Energy Journal, International Association for Energy Economics, vol. 0(Number 1), pages 87-54.
- P. L. Joskow & G. A. Rozanski, 1977.
"The Effects of Learning by Doing on Nuclear Plant Operating Reliability,"
Working papers
209, Massachusetts Institute of Technology (MIT), Department of Economics.
- Joskow, Paul L & Rozanski, George A, 1979. "The Effects of Learning by Doing on Nuclear Plant Operating Reliability," The Review of Economics and Statistics, MIT Press, vol. 61(2), pages 161-68, May.
- Rothwell, Geoffrey, 1990. "Utilization and service : Decomposing nuclear reactor capacity factors," Resources and Energy, Elsevier, vol. 12(3), pages 215-229, September.
- Richard K. Lester & Mark J. McCabe, 1993. "The Effect of Industrial Structure on Learning by Doing in Nuclear Power Plant Operation," RAND Journal of Economics, The RAND Corporation, vol. 24(3), pages 418-438, Autumn.
- Geoffrey Rothwell & John Rust, 1995. "A Dynamic Programming Model of U.S. Nuclear Power Plant Operations," Microeconomics 9502001, EconWPA, revised 06 Feb 1995.
- Sturm, Roland, 1993. "Nuclear power in Eastern Europe : Learning or forgetting curves?," Energy Economics, Elsevier, vol. 15(3), pages 183-189, July.
- David, Paul A & Maude-Griffin, Roland & Rothwell, Geoffrey, 1996. "Learning by Accident? Reductions in the Risk of Unplanned Outages in U.S. Nuclear Power Plants after Three Mile Island," Journal of Risk and Uncertainty, Springer, vol. 13(2), pages 175-98, September.
Citations
Lists
This item is not listed on Wikipedia, on a reading list or among the top items on IDEAS.Statistics
Access and download statisticsCorrections
When requesting a correction, please mention this item's handle: RePEc:mee:wpaper:1016For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: (Sharmila Ganguly).
If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.
If references are entirely missing, you can add them using this form.
If the full references list an item that is present in RePEc, but the system did not link to it, you can help with this form.
If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your profile, as there may be some citations waiting for confirmation.
Please note that corrections may take a couple of weeks to filter through the various RePEc services.