Scheduling with multi-attribute setup times on two identical parallel machines

Author

Listed:
  • Lee, Cheng-Hsiung
  • Liao, Ching-Jong
  • Chung, Tsui-Ping

Abstract

This paper considers a real-life identical parallel scheduling problem originating from the manufacturing plant producing polyvinyl chloride leather products. In the considered scheduling problem, each job has some attributes and each attribute has several different levels. Because there is at least one different level of attribute between two adjacent jobs, it is necessary to make a setup adjustment whenever there is a switch from processing a job to a different job on each machine. The problem can be classified as a scheduling problem to minimize the makespan on two identical parallel machines with multi-attribute setup times. A constructive heuristic, named COIT, is first proposed for the problem and evaluated by comparing with the current scheduling method used by the case plant. To further improve the solution, a variable neighborhood search (VNS) metaheuristic is presented and compared with a mixed integer programming model. The computational results show that the COIT heuristic outperforms the current scheduling method with a significant improvement, and the VNS can further improve the solution.

Suggested Citation

  • Lee, Cheng-Hsiung & Liao, Ching-Jong & Chung, Tsui-Ping, 2014. "Scheduling with multi-attribute setup times on two identical parallel machines," International Journal of Production Economics, Elsevier, vol. 153(C), pages 130-138.
  • Handle: RePEc:eee:proeco:v:153:y:2014:i:c:p:130-138
    DOI: 10.1016/j.ijpe.2014.02.013
    as

    Download full text from publisher

    File URL: http://www.sciencedirect.com/science/article/pii/S0925527314000620
    Download Restriction: Full text for ScienceDirect subscribers only

    File URL: https://libkey.io/10.1016/j.ijpe.2014.02.013?utm_source=ideas
    LibKey link: if access is restricted and if your library uses this service, LibKey will redirect you to where you can use your library subscription to access this item
    ---><---

    As the access to this document is restricted, you may want to search for a different version of it.

    References listed on IDEAS

    as
    1. A. Agnetis & P. Detti & C. Meloni & D. Pacciarelli, 2001. "Set-Up Coordination between Two Stages of a Supply Chain," Annals of Operations Research, Springer, vol. 107(1), pages 15-32, October.
    2. Tang, Christopher S., 1990. "Scheduling batches on parallel machines with major and minor set-ups," European Journal of Operational Research, Elsevier, vol. 46(1), pages 28-37, May.
    3. Liao, Ching-Jong & Shyu, Cian-Ci & Tseng, Chao-Tang, 2009. "A least flexibility first heuristic to coordinate setups in a two- or three-stage supply chain," International Journal of Production Economics, Elsevier, vol. 117(1), pages 127-135, January.
    4. Artigues, Christian & Lopez, Pierre & Haït, Alain, 2013. "The energy scheduling problem: Industrial case-study and constraint propagation techniques," International Journal of Production Economics, Elsevier, vol. 143(1), pages 13-23.
    5. Li, Shanling, 1997. "A hybrid two-stage flowshop with part family, batch production, major and minor set-ups," European Journal of Operational Research, Elsevier, vol. 102(1), pages 142-156, October.
    6. Imran, Arif & Salhi, Said & Wassan, Niaz A., 2009. "A variable neighborhood-based heuristic for the heterogeneous fleet vehicle routing problem," European Journal of Operational Research, Elsevier, vol. 197(2), pages 509-518, September.
    7. Liu, Ming & Wang, Shijin & Chu, Chengbin, 2013. "Scheduling deteriorating jobs with past-sequence-dependent delivery times," International Journal of Production Economics, Elsevier, vol. 144(2), pages 418-421.
    8. Allahverdi, Ali & Ng, C.T. & Cheng, T.C.E. & Kovalyov, Mikhail Y., 2008. "A survey of scheduling problems with setup times or costs," European Journal of Operational Research, Elsevier, vol. 187(3), pages 985-1032, June.
    9. C-J Liao & C-M Chen & C-H Lin, 2007. "Minimizing makespan for two parallel machines with job limit on each availability interval," Journal of the Operational Research Society, Palgrave Macmillan;The OR Society, vol. 58(7), pages 938-947, July.
    10. Pereira Lopes, Manuel J. & de Carvalho, J.M. Valerio, 2007. "A branch-and-price algorithm for scheduling parallel machines with sequence dependent setup times," European Journal of Operational Research, Elsevier, vol. 176(3), pages 1508-1527, February.
    11. Nait Tahar, Djamel & Yalaoui, Farouk & Chu, Chengbin & Amodeo, Lionel, 2006. "A linear programming approach for identical parallel machine scheduling with job splitting and sequence-dependent setup times," International Journal of Production Economics, Elsevier, vol. 99(1-2), pages 63-73, February.
    Full references (including those not matched with items on IDEAS)

    Citations

    Citations are extracted by the CitEc Project, subscribe to its RSS feed for this item.
    as


    Cited by:

    1. Allahverdi, Ali, 2015. "The third comprehensive survey on scheduling problems with setup times/costs," European Journal of Operational Research, Elsevier, vol. 246(2), pages 345-378.

    Most related items

    These are the items that most often cite the same works as this one and are cited by the same works as this one.
    1. Og[breve]uz, Ceyda & Sibel Salman, F. & Bilgintürk YalçIn, Zehra, 2010. "Order acceptance and scheduling decisions in make-to-order systems," International Journal of Production Economics, Elsevier, vol. 125(1), pages 200-211, May.
    2. Kramer, Arthur & Iori, Manuel & Lacomme, Philippe, 2021. "Mathematical formulations for scheduling jobs on identical parallel machines with family setup times and total weighted completion time minimization," European Journal of Operational Research, Elsevier, vol. 289(3), pages 825-840.
    3. Rauchecker, Gerhard & Schryen, Guido, 2019. "An exact branch-and-price algorithm for scheduling rescue units during disaster response," European Journal of Operational Research, Elsevier, vol. 272(1), pages 352-363.
    4. Timo Gschwind & Stefan Irnich & Christian Tilk & Simon Emde, 2020. "Branch-cut-and-price for scheduling deliveries with time windows in a direct shipping network," Journal of Scheduling, Springer, vol. 23(3), pages 363-377, June.
    5. Mansouri, S. Afshin & Aktas, Emel & Besikci, Umut, 2016. "Green scheduling of a two-machine flowshop: Trade-off between makespan and energy consumption," European Journal of Operational Research, Elsevier, vol. 248(3), pages 772-788.
    6. Allahverdi, Ali & Gupta, Jatinder N. D. & Aldowaisan, Tariq, 1999. "A review of scheduling research involving setup considerations," Omega, Elsevier, vol. 27(2), pages 219-239, April.
    7. Ching-Jong Liao & Cheng-Hsiung Lee & Hsing-Tzu Tsai, 2016. "Scheduling with multi-attribute set-up times on unrelated parallel machines," International Journal of Production Research, Taylor & Francis Journals, vol. 54(16), pages 4839-4853, August.
    8. Pohl, Maximilian & Kolisch, Rainer & Schiffer, Maximilian, 2021. "Runway scheduling during winter operations," Omega, Elsevier, vol. 102(C).
    9. Mac Cawley, Alejandro & Maturana, Sergio & Pascual, Rodrigo & Tortorella, Guilherme Luz, 2022. "Scheduling wine bottling operations with multiple lines and sequence-dependent set-up times: Robust formulation and a decomposition solution approach," European Journal of Operational Research, Elsevier, vol. 303(2), pages 819-839.
    10. Beezão, Andreza Cristina & Cordeau, Jean-François & Laporte, Gilbert & Yanasse, Horacio Hideki, 2017. "Scheduling identical parallel machines with tooling constraints," European Journal of Operational Research, Elsevier, vol. 257(3), pages 834-844.
    11. Hyun-Jung Kim, 2018. "Bounds for parallel machine scheduling with predefined parts of jobs and setup time," Annals of Operations Research, Springer, vol. 261(1), pages 401-412, February.
    12. Vallada, Eva & Ruiz, Rubén, 2011. "A genetic algorithm for the unrelated parallel machine scheduling problem with sequence dependent setup times," European Journal of Operational Research, Elsevier, vol. 211(3), pages 612-622, June.
    13. Ruiz, Rubén & Vázquez-Rodríguez, José Antonio, 2010. "The hybrid flow shop scheduling problem," European Journal of Operational Research, Elsevier, vol. 205(1), pages 1-18, August.
    14. Allahverdi, Ali, 2015. "The third comprehensive survey on scheduling problems with setup times/costs," European Journal of Operational Research, Elsevier, vol. 246(2), pages 345-378.
    15. Javad Rezaeian & Reza Alizadeh Foroutan & Toraj Mojibi & Yacob Khojasteh, 2023. "Sensitivity Analysis of the Unrelated Parallel Machine Scheduling Problem with Rework Processes and Machine Eligibility Restrictions," SN Operations Research Forum, Springer, vol. 4(3), pages 1-24, September.
    16. Marko Ɖurasević & Domagoj Jakobović, 2019. "Creating dispatching rules by simple ensemble combination," Journal of Heuristics, Springer, vol. 25(6), pages 959-1013, December.
    17. Dongni Li & Xianwen Meng & Miao Li & Yunna Tian, 2016. "An ACO-based intercell scheduling approach for job shop cells with multiple single processing machines and one batch processing machine," Journal of Intelligent Manufacturing, Springer, vol. 27(2), pages 283-296, April.
    18. Byung-Cheon Choi & Myoung-Ju Park, 2015. "A Batch Scheduling Problem with Two Agents," Asia-Pacific Journal of Operational Research (APJOR), World Scientific Publishing Co. Pte. Ltd., vol. 32(06), pages 1-19, December.
    19. Bozorgirad, Mir Abbas & Logendran, Rasaratnam, 2013. "Bi-criteria group scheduling in hybrid flowshops," International Journal of Production Economics, Elsevier, vol. 145(2), pages 599-612.
    20. Weng, Wei & Fujimura, Shigeru, 2012. "Control methods for dynamic time-based manufacturing under customized product lead times," European Journal of Operational Research, Elsevier, vol. 218(1), pages 86-96.

    Corrections

    All material on this site has been provided by the respective publishers and authors. You can help correct errors and omissions. When requesting a correction, please mention this item's handle: RePEc:eee:proeco:v:153:y:2014:i:c:p:130-138. See general information about how to correct material in RePEc.

    If you have authored this item and are not yet registered with RePEc, we encourage you to do it here. This allows to link your profile to this item. It also allows you to accept potential citations to this item that we are uncertain about.

    If CitEc recognized a bibliographic reference but did not link an item in RePEc to it, you can help with this form .

    If you know of missing items citing this one, you can help us creating those links by adding the relevant references in the same way as above, for each refering item. If you are a registered author of this item, you may also want to check the "citations" tab in your RePEc Author Service profile, as there may be some citations waiting for confirmation.

    For technical questions regarding this item, or to correct its authors, title, abstract, bibliographic or download information, contact: Catherine Liu (email available below). General contact details of provider: http://www.elsevier.com/locate/ijpe .

    Please note that corrections may take a couple of weeks to filter through the various RePEc services.

    IDEAS is a RePEc service. RePEc uses bibliographic data supplied by the respective publishers.